Image: Arena
A solar and battery-based microgrid installed on the World Heritage-listed Lord Howe Island on the coast of Australia in the Tasman Sea delivered more than $1.5 million in diesel fuel cost savings in its first two years of operation, a new report has revealed.
Commissioned in April 2021, the Hybrid Renewable Energy Project (HREP) was installed to provide a sustainable supply of electricity for the 400 residents and up to 400 tourists on Lord Howe Island, slashing its reliance on costly and polluting diesel fuel generation.
The $11.1 million project, developed by Photon Energy and backed by the Australian Renewable Energy Agency (Arena) installed 1.3MW of solar with a 3.7MWh Tesla battery energy storage system and micro-grid controller, alongside the existing diesel system of three 300kW generating units.
It received $4.5 million in funding from Arena, while the Lord Howe Island Board secured a NSW government loan of $5.9 million, providing the remaining balance of funds from its own capital.
Within its first six months of operation, the microgrid proved its worth, with reports emerging that the solar and battery system had navigated stretches of up to five days and nights powering the island without any additional diesel-generated back-up.
But in a knowledge sharing report published this week, Arena says the project has outperformed expectations on a number of fronts, including the average amount of renewables it supplies, forecast at 67%. And it has saved the island hundreds of thousands of dollars a year.
“Over the first 12-months of operation, HREP supplied approximately 1,587 MWh of renewable energy to the LHI grid. The average RE penetration was 73%,” the report says.
“Over the second 12-months of operation, HREP supplied 1,654 MWh of renewable energy to the LHI grid with an average RE penetration of 67.93% … owing largely to the wet autumn.”
The report also says that the microgrid saved 349,082 litres of diesel in the first year, delivering $740,054 in fuel cost savings based on an average supply price of 2.12 $/L (GST exc.). During the second, 360,236 litres of diesel was saved, delivering $815,641 in fuel cost savings based on an average
supply price of 2.26 $/L (GST exc.) – a total saving of around $1.55 million over two years.
The report also notes that the microgrid caused “zero interruptions” to the island’s power supply during the reporting period.
“The hybrid renewable energy project has improved Lord Howe’s self-sufficiency whilst also reducing the island’s reliance on diesel generators and imported fuels,” the report says.
“The project has enabled skill development by power station operators, LHIB personnel and island residents. The partnership with Arena means that knowledge about the Island’s hybrid renewable energy microgrid will be shared to the benefit of other remote communities in the future.”
Fossil fuel lobbyists are flooding social media with ads, outgunning the minimal effort of the…
Solar Sharer exposes a fundamental problem with our energy system – protecting retailer revenues can…
A policy designed to give households access to abundant free solar power has been nobbled…
As the party backed by Gina Rinehart burns effigies of renewable energy infrastructure, one of…
One Nation has promised to extend the life of a coal-fired power plant as part…
One Nation and Coalition plans to review or roll back Victoria's energy policies would likely…