Pumped Hydro

Snowy buys extra boring machine to support “disappointing” Florence as testing unearths more problems

Published by

Snowy Hydro says it will bring in a fourth tunnel boring machine in an attempt to keep the beleaguered Snowy 2.0 pumped hydro project to its already delayed timetble, admitting that the geology is even more complicated than previously thought.

Snowy Hydro CEO Dennis Barnes has already admitted once that the federal government owned utility had not done proper due diligence on the geology of the project, but now further studies have revealed even more complexity.

Barnes said in a statement last week announcing the new boring machine that the company knew about the fault zone that lies along the length of the head-race tunnel that often stuck Florence has been working on but the project design hadn’t been ‘mature’ enough to handle its complexity.

”While the fault zone is not a surprise, further ground testing since the project reset has revealed it is far more geologically challenging than earlier investigations indicated,” he said in the statement. 

“We’ve carefully considered a range of options to get through the fault zone and overcome the initial design immaturity.”

But Snowy Hydro’s own 2017 feasibility study noted that “geological, geotechnical and hydroecological conditions vary significantly along the alignment… five major underground rock mass groups, three major fault zones and five rivers and creeks affect the dam-to-dam alignment”.

The 2017 feasibility study detail on what engineers suspected might be under the ground.

The final investment decision outlined just how many unknowns there were when it came to the Snowy 2.0 geology, however.

The FiD outlined data gaps including that the 38 bores drilled along the full 26 km distance couldn’t provide enough information about “diverse ground conditions and lithological rock types” or to understand the already-known risks. It also noted granite rock in the area “could impact on the tunnel”.

A cool $75m

The new machine will cost around $75 million, but Snowy Hydro says this extra cost won’t add to the now blown out cost of $12 billion for building the 2.2 gigawatt (GW) pumped hydro scheme. 

It’s hoped that introducing another boring machine will keep Snowy 2.0 to its latest official deadline of December 2028, provided the New South Wales Department of Planning approves the change.

However, the machine won’t be on deck until the end of 2025.

The project currently will then have four boring machines working on three tunnel, including the original Florence machine, which by May had gotten just 850 metres into the 17 kilometre headrace tunnel.

A second machine is handling the pressure shaft above the power station; and a third is digging the tailrace tunnel leading to the lower talbingo reservoir.

The fourth machine will start at the other end of the headrace. It will be made and supplied by Germany’s Herrenknecht, the same company that made the Florence tunnelling machine and supplied one of the other borers.

This is despite Barnes specifically criticising the performance of Florence – which has been stuck in soft earth and then hard rock – as “disappointing”.

Renew Economy is seeking further comment from Snowy Hydro.

Then-prime minister Malcolm Turnbull announced the project in 2017 with the highly optimistic figure of $2 billion and a finishing date of 2021.

The feasibility study, released at the end of 2017, said it was more likely to cost $3.8-4.5 billion and be ready by 2024. But actual construction costs combined with myriad problems, such as the Florence boring machine getting stuck in soft earth, then hard rock have sent the costs skyrocketing.

This year, the federal government allocated $7.1 billion over four years to the project, with $2.6 billion in equity funding and the remainder as a loan.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024