Storage

Scotland launches giga-scale big battery rollout to boost grid reliability

Published by

British EV fleet and battery storage specialist Zenobē has announced the beginning of construction on three battery storage projects across Scotland which, when complete, will together boast capacity of 1GW/2GWh.

Totalling an investment of £750 million, the three projects include the 300MW/600MWh Blackhillock project, with the 200MW/400MWh first phase due to go live in the first half of 2024.

The 300MW/600MWh Kilmarnock South project has a first 200MW/400MWh phase due to go live in the second half of 2024, while a 400MW/800MWh Eccles project is due to go live in the first half of 2026.

Construction at the Blackhillock site got underway this month, following Zenobē’s 50MW/100MWh battery project at Wishaw, which is expected to go live in the first half of 2023. The Wishaw battery storage project is the first to win a constraint management contract and the first in Scotland to connect directly to the transmission network.

All four projects serve to deliver a project portfolio for Zenobē of 1,050MW/2,100MWh.

Image: Zenobē
Image: Zenobē

Over the planned 15 years of operation the three sites are expected to save up to 13.4 million tonnes of CO2 and help to lower consumers bills by over £1 billion by reducing the curtailment of windfarms over the same period.

Each of the three battery projects are contracted to provide stability services to the UK’s National Grid Electricity System Operator (NGESO), helping to improve the reliability of the UK’s growing renewable energy sources.

Moreover, these are reportedly the first commercial contracts in the world to use transmission connected batteries to provide short-circuit level and inertia, an essential tool for the grid to function efficiently as fossil fuel plants are continually phased out of operation.

World firsts

“Zenobē is transforming the uptake of clean power, enabling the UK to become both more independent and greener in how it generates electricity,” said James Basden, co-founder and director of Zenobē.

“These projects are using the latest technological innovation to make renewable energy more reliable and affordable at a national scale. This is the future for how utility scale battery projects will work on every grid.

“Our projects at Blackhillock, Kilmarnock South and Eccles are world-firsts for battery storage, addressing a key, complex hurdle to the uptake of renewables in an innovative way and pushing forward our progress to energy independence and a zero-carbon grid.”

The deployment of large-scale battery storage is particularly important in a country like Scotland, which currently uses 96% carbon-free generation. The rapid rollout of wind power across the country has meant the transmission network is becoming more congested, leading to the expensive shutdown of wind farms.

As such, the location for each of the three Zenobē battery storage projects was chosen specifically to help reduce this curtailment, allowing for more power to reach the grid, helping to lower bills for consumers and increase the UK’s energy independence.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by
Tags: big battery

Recent Posts

Virtual networks and the real pursuit of energy democracy | Solar Insiders

Deakin University’s Andrea La Nauze on the early findings from an Australia-first trial of technology…

1 July 2026

Plan to power off-grid data centre with solar, gas and a 16 gigawatt-hour battery seek federal green tick

Project Ares wants to build a 1 GW data centre on a cattle station on…

1 July 2026

Renewables generate record share of UK electricity, as wind out-supplies gas

Renewable energy sources across the UK generated a record share of the country’s electricity in…

1 July 2026

Green hydrogen hopes lift as “headstart” project reaches crucial financial milestone

Just two projects were funded under Hydrogen Headstart and one has just reached FID, with…

1 July 2026

“Boom far from over,” but 2025 goes down in history as the year home batteries went mainstream

New report released on first anniversary of Cheaper Home Batteries scheme confirms 2025 as a…

1 July 2026

Solar Sharer is here, offering free power to all. Will it level the playing field, or benefit batteries most?

Solar Sharer may have been sold as an consumer equity policy, but it could have…

1 July 2026