The 200MW/400MWh Greenbank Battery project in Logan in south east Queensland has kicked off commercial operations, according to developer CS Energy, including regularly charging and discharging to support market requirements.

Queensland government owned generator CS Energy said on Thursday that the two-hour battery, comprising 108 Tesla Megapack 2XL units, started commercial operations last month in its role soaking up excess solar and boosting the reliability the local grid.

“The battery has gone through a rigorous testing and commissioning process, which was similar to the approach used for the Chinchilla Battery,” said CS Energy chief Brian Gillespie. 

“CS Energy also undertook a detailed operational readiness program, which included employee training, critical risk assessments, and safety and design reviews. 

“Thank you to local residents who attended community updates held by our team during the construction phase. I would like to reaffirm our commitment to being a good neighbour now that we are in the operations phase.” 

Image: CS Energy

CS Energy built the two-hour big battery adjacent to Powerlink’s Greenbank sub-station on the south-side of Brisbane, as part of a “battery blitz” launched in the wake of an explosion at the Callide coal generator back in 2021.

Greenbank is CS Energy’s second grid-scale battery energy storage system (BESS), following the commissioning of its Chinchilla BESS in 2024.

It was the also state’s biggest when first announced, but has since been surpassed by a number of projects, namely Neoen’s 270 MW / 540 MWh Western Downs Battery, which started the energisation process in June of 2024.

A second stage for the Western Downs project, announced in August 2024, will double its size to 540 MW and 1080 MWh.

CS Energy says it worked with Tesla, Consolidated Power Projects, and Powerlink Queensland to deliver the Greenbank Battery. Two experienced “operator maintainers” have been employed in permanent, on-site roles to support operation of the BESS.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Can EVs help get more out of the grid, for less? Two new grant winners hope to show the way

New Federal government grant package backs 14 projects to get more renewables on the grid,…

22 July 2026

Government backs “disaster proposal” to power hyperscale data centre with fracked Beetaloo gas

NT government has set aside land for the $40 billion gas-powered AI ambitions of ASX-listed…

22 July 2026

Solar and battery to deliver 80 pct of remote off-grid gold mining town’s power supply

Transition of an off-grid gold mining town from diesel to mostly solar and battery to…

22 July 2026

SwitchedOn podcast: Why more consumers want less to do with the energy system

Energy Consumers Australia's Ashley Bradshaw on the results of the latest consumer Report Card, and…

22 July 2026

China home battery brand that blitzed federal rebate unveils new product – and its next market target

After dominating sales in the first year of the federal Cheaper Home Batteries rebate. China…

22 July 2026

Construction starts on new wind farm as leading developer switches to new Chinese-made turbines

One of Australia's leading wind developers has switched to new Chinese turbines in a potentially…

22 July 2026