Solar farm at Rio Tinto's Weipa mine.
The Weipa solar PV facility is the first of what is expected to be many mining facilities to turn to solar PV and other technologies for reduce the costs of electricity, which even with a falling oil price is still expensive.
For the moment, however, Australian miners are still unwilling to divert their own funds to such programs, with both the Weipa and the Degrussa projects being largely funded by the Australian Renewable Energy Agency, and in the case of Degrussa, by the Clean Energy Finance Corporation as well.
ARENA CEO Ivor Frischknecht said the funding is justified because the Weipa project could bolster the mining industry’s confidence in renewable energy as a reliable off-grid power source.
“The success of phase one is set to create a precedent for industry by demonstrating that solar PV is a viable option for powering off-grid locations, like mine sites, in Australia.”
ARENA provided $3.5 million for the first part of the project and will provide up to $7.8 million for the second phase, which could reduce the consumption of diesel by around 2.3 million litres of diesel a year, and provide the majority of its power requirements.
The facility was built by US solar manufacturer First Solar.
The grid is changing rapidly, battery storage durations are getting longer, and chemistries are changing…
Allowing balcony or plug in solar will make it easier to access cheaper, cleaner electricity…
Industry expert Claire Elkin on why Australia is missing out on global capital to fund…
MELBOURNE, Australia, 28 October 2026 — Fox ESS (Fox) showcases Power Beast, G-Max Plus, Power…
Join our experts to explore how expanded rebates could unlock an 80 GW market and…
Australia is home to 163 operational data centres with almost 100 more in the national…