RES switches on spinning machine to support big Victorian wind farm

Published by

Renewable energy developer RES has announced that it has switched on a synchronous condenser – a big spinning machine that provides system strength to the grid – to support the second stage of its Murra Warra wind farm in western Victoria.

The inauguration of the 60Mvr syncon has enabled the Murra Warra 2 wind project to leap to the next “hold point” of its commissioning process – 150MW – before moving towards its full capacity of 209MW.

Murra Warra is located in a relatively weak part of the grid – in the West Murray region and on what has become known as the “rhombus of regret”, largely because of the shape of the local network and the constraints that were imposed on new wind and solar farms in the area.

The wind project was required to install the syncon as part of the now abandoned “do no harm” rules that put the responsibility of solving system strength issues in a particular region onto new projects. That responsibility has now been shifted to the transmission network operators.

RES says the syncon, supplied by GE along with the turbines, will support system strength in the West Murray region for the stable operation of the wind farm, as well as other renewable generators in the area. 

Anthony Berzi, the head of construction of RES, said while there had been criticism from many quarters about construction and commissioning delays, he wanted to acknowledge the flexibility and co-operation of the market operator, AEMO, which has responsibility for connections in Victoria.

“It’s great to see the working relationship that RES has fostered with AEMO has enabled a collaborative effort to resolve the technical challenges that have confronted the project,” he said in a statement.

“RES believes that without the tireless work of the AEMO team, the project would not be as advanced as it is.”

Both the 220MW Murra Warra 1 and the 209MW Murra Warra 2 wind projects are owned by Partners Group, after being initially developed by RES and Macquarie, the latter’s first major move into wind generation in Australia.

Murra Warra 1 has a long term contract with Telstra and other corporate buyers for the bulk of its output, while Murra Warra 2 struck a deal in 2019 for a long term contract with Snowy Hydro for what was then described as record low prices in the low $40/MWh.

That compares to the average wholesale electricity price across the main grid in the June quarter of nearly seven times that much. RES has the construction and asset management contract.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Renewables hit more than 80 pct of grid demand for first time – despite heavy throttling of wind and solar

Renewables met more than 80 per cent of total grid demand for first time on…

19 September 2026

Explainer: Who will set Australia’s rules for home energy devices such as solar, plug-in batteries and EVs?

A new Consumer Energy Resources Technical Code will define the standards and capabilities required of…

19 September 2026

Businesses “do the math” and want to go electric – right up until they try to connect to the grid

Australian businesses looking to ditch gas and diesel can do the sums, find electrification will…

18 September 2026

Wind and solar hit record share of Australia’s main grid, nearly half of it from rooftop PV

An abundance of rooftop solar generation has helped set a new record high for the…

18 September 2026

Energy Insiders: The “impossible” wind project that broke the investment drought

Windlab's John Martin on the project that broke the investment drought for big wind, and…

18 September 2026

“Massive loophole:” Consultation paper stokes doubt on data centre emissions, wind and solar mandates

Federal Labor's determination to power new data centres with renewables, and to minimise emissions and…

18 September 2026