Queensland’s biggest wind farm powers up near Mareebra

Published by

Queensland’s biggest wind farm to date, the 180MW Mount Emerald facility near Mareebra, is powering up, as the project that signalled a change in the Australian wind industry’s fortunes back in 2015 nears completion.

Project developers Ratch Australia said on Tuesday that the first of the wind farm’s 44 completed Vestas turbines (six more are yet to be fully erected) had started to turn as part of a staged testing and commissioning process. 

Ratch said the tests were a “significant milestone” in Mount Emerald’s “electrification,” with the completion of the site’s substation and switchyard which were now energised and sending the power generated to the grid.

“It’s a very important milestone and is the culmination of lot of work by a lot of people over a very long period of time,” said Ratch head of business development, Anthony Yeates

“We’ve now commenced generating electricity and sending it into the grid, and we’ll be ramping up the amount of generation over the next few months as additional turbines get commissioned,” he said.

“We’ve invested thousands of hours into site preparation and building the project and now we get to see it in action and producing electricity.

“It is very satisfying this has come together like we planned and it’s a great payoff for all our hard work, particularly for many local suppliers who have been with us from the start.”

As we reported here, the $380 million wind farm had a rocky road to approval, before finally getting the green light from the notoriously anti-wind Coalition federal government in November 2015, marking a change in sentiment in the national market and the arrival of large-scale wind energy in Queensland.

Before then, Mount Emerald had come up against significant local opposition, and in June 2014, then Deputy Premier Jeff Seeney called in its development application, taking responsibility for approval away from the Mareeba Shire Council.

Once approved, the project sealed a power purchase agreement in 2016 with regional utility Ergon to buy all its output until 2030, to help the network and energy retailer meet its renewable energy targets. Financial close followed soon after, with finance from ANZ, NAB, Societe Generale and the Mitsubishi UFJ Financial Group (MUFJ).

Ratch said this week that the remaining construction and turbine installation activities would be completed alongside turbine commissioning over the next few months, with full operation expected to commence in November this year.

Yeates said he was also very pleased with the efforts on site to ensure the project had delivered a high level of protection to the local ecology.

“We’ve had various teams of specialists on site who have worked very hard to make sure the procedures for protection of cultural heritage, flora and fauna have been carefully integrated into our work, as well as processes to ensure any unexploded ordinance on the site was carefully managed.

“At times this work introduced new challenges, but we are proud of the outcomes and consider we have probably set some sort of benchmark for future projects” he said.

The wind farm will deliver around 530,000 megawatt-hours of renewable energy – enough to power about 75,000 north Queensland homes over a 20-year period – and boost Queensland’s renewable energy credentials significantly, Ratch said.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“This is waste-washing:” Waste-to-energy projects called out for being dirtier than coal

Waste-to-energy incinerators should not be called clean, renewable, or low emission because they are as…

16 July 2026

Solar contractor files big claim against Shell over disputed cost overruns at Australian PV project

One of biggest solar contractors in Australia has lodged a major claim against Shell Energy…

16 July 2026

Australia is stuck in a vicious circle of diesel fuel dependence. Chinese electric trucks offer a way out

Australia remains extraordinarily dependent on imported diesel to move freight and support much of its…

16 July 2026

Wind, solar and storage remain cheapest new-build generation, says Lazard, despite rising costs

Annual analysis by Lazard confirms wind, solar and storage remain cheapest new build, despite pressures…

16 July 2026

Australia’s biggest coal port allowed to store big batteries as it transitions to major renewable gateway

Australia's biggest coal port given approval to store big batteries on site as it continues…

16 July 2026

Biggest ever turbines set sail for Australia, headed for Fortescue’s first wind project in Pilbara

The most powerful wind turbines to be installed in Australia set sail for Fortescue iron…

16 July 2026