Press Releases

Substation powers up for Mt Emerald Wind Farm project

PRESS RELEASE

Queensland’s largest wind farm — located in Far North Queensland — is now exporting its first electricity into the grid, with its new substation and switchyard now energised and ready to roll.

Energy Minister Dr Anthony Lynham said the 275kV Walkamin Substation, owned and built by Powerlink, had been commissioned and was already transporting power from Ratch Australia’s Mt Emerald Wind Farm into Powerlink’s transmission network.

“This new substation is the critical link to transport power generated at Mount Emerald,” Dr Lynham said.

“When testing and commissioning works are fully completed, the facility is expected to provide enough power annually to supply  up to 75,000 homes – equivalent to supplying about one third of Far North Queensland’s energy needs.

“With the substation energised, Ratch is now working through a phased commissioning and testing. All works are on schedule to have Mount Emerald fully operational and powering Queensland by the end of the year.”

The wind farm has created around 150 jobs during construction, with Powerlink’s grid connection works supporting another 59 jobs.

Shipments of all the major components saw more than 185,000 tonnes of cargo – blades, towers and generators – brought through the Port of Cairns for the wind farm’s construction. Road transport of these components from Cairns through to the site is now nearly complete.

The $380 million Mount Emerald Wind Farm is one of 13 renewable energy projects either underway or financially committed in North Queensland.

With a combined capital investment of more than $2 billion in the North Queensland economy, the projects will create more than 1,800 jobs during construction and generate a total of more than 1000 megawatts of electricity.

Powerlink Chief Executive Merryn York congratulated the Powerlink team who delivered the connection project works ahead of schedule.

“We worked closely with Ratch to accelerate the commissioning date for the Walkamin Substation by 10 weeks,” Ms York said.

“This was no easy feat, given the hilly and rocky terrain in the area which presented a number of design and technical challenges.”

Share

Recent Posts

Wind, solar and battery records tumble on last day of Autumn in Australia’s most coal dependent grid

Renewable records usually fall in spring, but in Australia's most coal dependent grid a new…

1 June 2026

“Just as common as solar-hybrids:” Most developers now including batteries in plans for wind

Developers are now adding batteries into their plans for wind projects, and manufacturers are beginning…

1 June 2026

BHP vs Fortescue in the Pilbara: Who is really building Australia’s post-diesel future?

BHP once represented scale and an ability to shape the future. Now it acts as…

1 June 2026

Proposal for high fixed network charges is wrong on home batteries, dynamic pricing, and impact on CER

The pricing review proposing high fixed network tariffs has got it wrong on home batteries,…

31 May 2026

Delays at Australia’s most powerful battery led to a more than $90 million cut in payments

Regulator quantifies the revenue cuts caused by the delayed start of the giant shock absorber"…

30 May 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

From renewables lobby to Squadron in a single bound, Fortescue leader calls time on 13-year…

30 May 2026