Queensland coal giant unveils plans for 500MW state-owned wind farm

Published by

Queensland government-owned energy giant Stanwell Corporation has unveiled plans to build a 500MW wind farm, as part of a shift from coal power generation to renewables that includes previously announced plans to install a big battery at its Tarong Power Station.

Stanwell said on Monday that it was working with global renewables developer RES to develop the proposed Tarong West wind farm at a site in Ironpot, 30km south-west of Kingaroy in the Southern Queensland Renewable Energy Zone.

The project, which remains subject to a board approval and shareholding minister approval, has been awarded $776 million in funding through the Queensland Renewable Energy and Hydrogen Jobs Fund.

In a government statement on Monday, Queensland premier Annastacia Palaszczuk described the project as Australia’s largest publicly owned wind farm.

Stanwell CEO Michael O’Rourke says the company proposes to take 100 per cent ownership and operation of the wind farm once it is built.

The state-owned corporation, which owns and operates the 1,460MW Stanwell coal power plant alongside the 1,400MW Tarong generator, announced a pivot away from fossil fuels and towards renewables in April of 2021.

At the time, Stanwell – which had suffered a $720 million hit to profits the year before – said it saw no future for new coal, and would operate its remaining two plants more “flexibly” for the remainder of their useful lives, potentially putting them in “standby” mode before retiring them altogether.

A month later, in May of 2021, Stanwell announced plans to develop a 150MW, two-hour big battery, to be co-located at the Tarong Power Station.

The energy market is changing, and so are we

In a statement on Monday, O’Rourke said that the firming up of the company’s large-scale renewable energy generation plans marked a significant milestone on the path to transformation of its business.

“The energy market is changing, and so are we,” he said.

“Strategic partnerships with renewable energy projects such as Tarong West Wind Farm are critical to us supporting our customers decarbonisation goals, as well as our own.

“Full ownership of the Tarong West Wind Farm project would support the decarbonisation of our existing portfolio, enable us to meet our customers’ demand for renewable energy products, and provide future career development opportunities for our people,” O’Rourke said.

RES is well-placed to help deliver the project for Stanwell, with more than over 1.1 GW of renewable energy projects under construction or in operation in Australia, alone.

CEO Matt Rebbeck says the proposed Tarong West wind farm will generate enough renewable energy to power around 230,000 homes and create around 200 direct local jobs during construction, and 15 ongoing operational roles.

The Tarong West Wind Farm is anticipated to reach Financial Investment Decision in Q2 2024. Construction of the wind farm is expected to commence in 2024, with anticipated commercial operations from 2026.

Queensland is ramping up its shift to renewables, too

Queensland Labor is expected this week to announce a higher renewable energy target for 2030, and also to  acknowledge that coal power is not needed over the longer term.

Palaszczuk said on Monday that investments like this, in the Tarong West wind farm, would help ensure the state delivered on its net-zero ambitions.

“We are now focused on what the next decade will look like, and I’ll have a lot more to say on this in this week’s CEDA State of the State address,” the premier said, hinting at the details of the Queensland energy plan that are expected to be unveiled at the CEDA event in Brisbane on Wednesday.

State energy minister Mick de Brenni said renewable energy was the cheapest form of electricity and that the Palaszczuk government was serious about becoming a global renewable energy powerhouse.

“It provides assurance that Queensland will be able to deliver on its promise of affordable and reliable power for new industries and new manufacturing sectors in the clean energy era of tomorrow,” De Brenni said.

“By growing our publicly owned portfolio of clean energy generation, it means Queenslanders will continue to control their energy system as it transforms to lower emissions.”

See also Queensland reaches 66 pct wind and solar for first time as it prepares massive green push

See RenewEconomy’s Large-scale Wind Farm Map of Australia

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024