Storage

Australia’s biggest battery project nears first production as it enters grid management system

Published by

The first stage of what will be Australia’s biggest battery storage when complete is getting ready to charge up for the first time after officially entering the market operator’s grid management system.

The preparations at the Eraring battery are significant for a number of reasons. The battery will eventually be sized at 700 MW and 2,800 MWh, bigger than any other battery currently operating or under construction in Australia.

It is also located on the same site as the Eraring coal fired power generator, which at 2,880 MW is also the biggest in the country, and is due to close in 2027 (or maybe 2029) after its owner Origin Energy winning government backing to stay open for another two years.

But nothing says an energy transition quite like a big flexible battery taking the place of a big baseload coal fired power station, and it is happening across the grid – at Hazelwood, Collie, Munmorah, Liddell, Mt Piper, Stanwell, – and also at a number of gas fired power stations.

The first stage of the Eraring battery will be sized at 460 MW and 920 MWh, and will add to the rapidly growing capacity of battery storage on the NSW grid.

Until recently there were only a couple of big batteries in operation in NSW – at Darlington and Wallgrove – but the commissioning of the massive 850 MW and 1680 MWh Waratah Super Battery will add to the armoury for the market operator, and a large number of batteries are now under construction, or about to start.

The Eraring battery’s entrance to the AEMO’s Market Management System (MMS) was noted by GPE NEMLog analyst Geoff Eldridge, who notes that this effectively marks the start of testing and commissioning to ensure it meets its agreed Generator Performance Standards (GPS).

The second stage of the battery is being at 240 MW and 1,030 MWh and has already begun construction. A third phase will add 700 MWh of storage to bring the total to 700 MW and 2,800 MWh.

Once completed, the site will span 17 hectares and house over 2,000 battery enclosures, reinforcing its role in supporting grid stability as more wind and solar generation come online. The battery provider is Finnish group Wärtsilä.

See also: Renew Economy’s Big Battery Storage Map of Australia.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Solar and wind remain “backbone” of least-cost future grid, as batteries squeeze gas to a fraction of the mix

Firmed solar and wind still lowest-cost pathway for Australia to reach net zero emissions, new…

15 July 2026

Hunter Valley collieries to be greened-up as clean industrial hubs in “post mining land transformation”

State and federal governments aim for 7,000 green and industrial jobs under new master plans…

14 July 2026

“We cannot wait:” Changes made to renewable tenders to ensure wind and solar projects actually get built

Key changes have been made to renewable tenders to ensure that the winning projects can…

14 July 2026

Coal closure delays and soaring prices mean more batteries and fewer syncons to keep heartbeat of grid

Soaring syncon costs and supply issues, along with delays to coal closures, is opening up…

14 July 2026

Spitting chips: A deep dive into the data and token industry, and who carries the GPU risk

This note provides an estimate of demand and supply of tokens, draws a conclusion about…

14 July 2026

Wind project with an 8-hour battery hybrid looks for final green light after speeding through state approvals

A new wind-battery hybrid project speeded through state approvals, now it needs one more nod,…

14 July 2026