Port Augusta wind hub resumes production after 3-week hiatus caused by “flickering”

Published by

The Port Augusta Renewable Energy Park, which will be Australia’s biggest wind and solar hybrid facility once complete, has resumed production after a three week hiatus caused by oscillation issues that caused “flickering” in the South Australia grid late last month.

Production was halted at PAREP on June 24 after repeated “flickers” and voltage fluctuations were experienced on the local grid the previous night.

Energy authorities identified the source of the problem as the new Port Augusta Renewable Energy Park, which is owned by Iberdrola Australia and will have a combined capacity of 317MW, making it the biggest of its type in the country.

Production was immediately halted at Parep, which had been working its way through the various stages of commissioning of the wind component of the facility, and had reached an output of around 140MW, out of its total capacity of 210MW.

The 107MW solar component is largely complete but has not yet started its commissioning process. It will operate as a separate generating unit despite being co-located, with its own DUID (market identifier).

Source: NEMLog.

This week, production at PAREP resumed, albeit at very low levels, initially at just a few megawatts, occasionally up to 20MW, and back down again.

RenewEconomy understands that output will continue to be volatile as part of testing to satisfy the transmission operator ElectraNet and the market operator AEMO that the plant’s settings have been fixed.

Once resolved, the wind component will be able to resume at its most recent “hold point” setting of 140MW, before being allowed to move to higher output levels as the commissioning process continues.

Earlier this week, production resumed at the Walkaway wind farm in Western Australia, also owned by Iberdrola, after more than one month offline following the still unexplained collapse of one of the facility’s 54 wind turbines.

 

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Offshore wind sector feeling the Dutton effect, even from the shadows of opposition

Labor's offshore wind plans are under fire from all corners of the conservative political and…

4 March 2025

First women-only rooftop solar project powers up in Victoria, sets higher bar for industry

It's common to see a group of blokes working away on a rooftop solar installation,…

4 March 2025

Australia’s biggest battery project nears first production as it enters grid management system

The first stage of what will be Australia's biggest battery has entered the grid management…

4 March 2025

Record year for renewable PPAs features two mega-deals – and a new biggest spender

2024 State of the Market report for corporate renewable power purchase agreements reveals another record…

4 March 2025

A summer of record renewables, record demand highs and record demand lows, and no blackouts

Australia's main grid boasted a record share of renewables over summer, and experienced record demand…

4 March 2025

Victoria urged to back home batteries and more deep storage, and do it soon

Draft strategy says batteries of all sizes - and deep storage - are critical to…

4 March 2025