Perth wave project achieves new first: 10,000 hours continuous operation

Published by

The world’s first grid-connected wave energy array – the Perth Wave Energy Project off Garden Island in Western Australia – has achieved a new first: the longest continuous period of operation of any in-ocean wave energy project.

The project’s Australian developer, Carnegie Wave Energy, said the “significant milestone” was achieved last week, when the array clocked up 10,000 hours of cumulative, continuous operation.

The array, at one time comprising three of Carnegie’s home-grown 240kW CETO 5 units (see image above), had seen a wide range of sea states during this time, the ASX-listed company said, including waves of up to 5.7 metres in height.

“Achieving 10,000 hours of continuous operation is a significant milestone not just for Carnegie but for the wave energy industry as a whole,” said Carnegie Wave CEO, Michael Ottaviano.

“The industry has faced a lot of challenges, especially around reliability and survivability. By demonstrating the continuous operation of our product, we’re addressing these challenges.

“Our understanding is that this is the longest continuous period of operation any in-ocean wave energy project has ever achieved, anywhere in the world.”

In May, the first of the CETO 5 units deployed for the Perth array was retrieved from the ocean, having achieved more than 8,500 hours of operation,  validating Carnegie’s ‘hot swap’ maintenance strategy.

Carnegie is currently working on a large-scale CETO 6 project, for which it secured funding in February.

The CETO 6 array site will be located around 8km further offshore from the current Perth Project, the company says, with the exact location yet to be determined. Once installed, it is expected to yield some three times more energy than the existing array.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

It needs to be more than big batteries: The triumphs and failures of Australia’s green energy transition

AEMO reports record number of newly commissioned projects in last fiscal year, but wind and…

20 July 2026

New data centre demand over next four years will be just a fraction of new home battery capacity

The increase in data centre demand is being overshadowed by the much larger increase in…

19 July 2026

Solar Insiders Podcast: Why new rules for networks signal a new dawn for consumers

AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…

17 July 2026

Developer lands “complete funding package” to begin building state’s largest solar-battery hybrid

Developer says it is good to go on early works and construction of the largest…

17 July 2026

“A really big game-changer:” AEMO looks to battery inverters as syncons prove expensive and hard to find

AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…

17 July 2026

Twiggy Forrest’s Squadron abandons plan for troubled New England wind farm

Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…

17 July 2026