Parts for biggest wind turbine arrive at NSW port, headed for Bango project

Published by

The first shipment of super-sized General Electric wind turbine components destined for the 224MW Bango wind farm, which is in the early stages of construction in the New South Wales Southern Tablelands, have arrived at Port Kembla.

NSW Ports said the wind turbine components had arrived this week, the first of many to be imported through Port Kembla over the next six months for the 46-turbine project.

Bango is being developed by Australian outfit CWP Renewables around 30km north of Yass. The project was last year reported to be the first in the world to use General Electric’s Cypress 5.3MW turbines, which rank amongst the largest onshore wind turbines currently in production, and is believed to be the biggest to be installed so far in Australia.

As you can see in the graphic below, the turbines will have a hub height of 121 metres, and a blade length of 79 metres, meaning the maximum height of the turbines will reach 200 metres.

For CWP Renewables, the wind farm is the third for the company in NSW, in partnership with global investment management firm Partners Group, including the completed 270MW Sapphire Wind Farm and the under-construction 135MW Crudine Ridge wind farm.

CWP is also leading the huge Asia Renewable Energy Hub consortium in the Pilbara region of W.A. which is looking at building 15GW of wind and solar capacity to support local industry and to export to Asia either as “green hydrogen” or possibly through a sub-sea cable.

NSW Ports said the Bango wind turbine components would be stored on berth at the AAT facility before being transported by truck to the project site, ready for assembly.

Image Source: Infrastructure Magazine
Image Source: Infrastructure Magazine

“We are proud to work with our partners in the supply chain to support these important renewable energy projects for our state,” said NSW Ports CEO Marika Calfas in a statement.

“With the addition of the Bango wind turbines, Port Kembla will have helped facilitate the import of 274 wind turbines for nine wind farms in NSW.

“This important trade is only possible because of the work of stevedores and specialist heavy haul logistics providers, who have the complex task of discharging the oversized cargo from the vessel and transporting them to the wind farms across regional New South Wales,” Calfas said.

The Bango wind farm Facebook page said the wind turbine parts would be following the below route, and would be travelling mostly in the morning, and returning unloaded from midday onwards – before or after school buses were on the road.

TURBINE COMPONENT DELIVERIES TO BANGO WIND FARM

Wind turbine components will soon be arriving to the Bango Wind Farm on…

Posted by Bango Wind Farm on Sunday, July 19, 2020

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Second stage of Supernode battery begins operations, making it the biggest in Australia’s main grid

Second stage of huge Supernode battery project starts operations, making it the biggest battery in…

28 July 2026

Victoria is in a real energy pickle, and now has a new premier. One Nation is not the solution

Voters in Victoria are angry about the rising cost of living. But One Nation will…

28 July 2026

GenCost: The seven caveats behind CSIRO’s “No Progress” scenario – and why it isn’t cheaper

Some stakeholders have used CSIRO's No Progress GenCost scenario to argue net zero should be…

28 July 2026

Outrage machine winning as Australians worry that others don’t support energy transition

Support for renewables is not where it needs to be to get the energy transition…

28 July 2026

“Makes no sense:” Labor mulls third oil refinery as analysts urge faster push into EVs

Energy and climate experts say Labor's plan for a third oil refinery in Australia makes…

28 July 2026

Queensland utility writes long term PPA for one of state’s biggest wind projects – a first under LNP government

Queensland state owned utility signs first major PPA since election of LNP government two years…

28 July 2026