One of the first large scale solar farms built in Australia – the 13.3MW (ac) Mugga Lane Solar Park, has gone into voluntary administration and has been put up for sale.

Scott Langdon and David Osborne of KordaMentha were appointed as voluntary administrators of Mugga Lane Solar Park last week, even though the facility has a lucrative and long term off take agreement with the ACT government.

Mugga Lane was one of seven wind and solar farms that won the ACT government’s first tender on its way to its target of sourcing the equivalent of 100 per cent of its electricity from renewables.

Mugga Lane’s contract was for a guaranteed price of $A178/MWh, which appears a huge number in the current environment where strike prices are expected to be less than one third of that.

It’s not entirely clear what’s gone wrong. The KordaMentha statement says only the appointment  was necessary due to the “recent external effects on the financial arrangements” of Mugga Lane Solar Park.

It is understood the owners of Mugga Lane, Maoneng, had been seeking to refinance the facility, which is housed in a special purpose vehicle.

Why problems have emerged at Mugga Lane given the long term contract with a government entity at such a high price, and given there appears to be no operational problems, is not clear.

Maoneng has been announcing a whole series of large scale solar and battery storage projects, but it insists it will not be impacted by the situation at Mugga Lane.

“Mugga Lane Solar Park is a group subsidiary asset operating under a special purpose vehicle structure,” a Maoneng spokesperson said in a statement.

“The appointment of KordaMentha, the voluntary administrators, only relates to Mugga Lane Solar Park, and does not affect other group operations or any related entities.”

Just last week Maoneng announced proposals for a 550MW solar farm and a 1600MWh battery in NSW. It also has a contract to deliver 400MWh of battery storage to AGL and has a small stake in the 200MW Sunraysia solar farm.

It has also secured planning approval to build the biggest battery in South Australia, plans to develop a 2GW solar pipeline, and separately a 240MW/480MWh big battery in Victoria.

The Mugga Lane solar park is built on a 52-hectare site in the south of Canberra, was completed in March, 2017, and generates approximately 24,500MWh of electricity a year.

“Mugga Lane Solar Park will continue to operate on a ‘business as usual’ basis and there will be no disruption to operations or any stakeholders,” KordaMentha’s Langdon said in a statement.

“The Voluntary Administrators will work collaboratively with the director to run an international sale process and maximise competitive tension and the financial outcomes for all stakeholders and creditors.”

Langdon said he expected a high level of international interest in the Mugga Lane solar park due to the unique nature of the asset. “We encourage anyone interested in purchasing the Mugga Lane Solar Park to contact our office immediately,” he said.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…