Solar

NSW abattoir goes back for seconds on solar, adds a battery to cut dependence on the grid

Published by

A sheep abattoir in New South Wales’ (NSW) Riverina is doubling the size of its solar farm and adding a battery as it seeks to dramatically reduce its dependence on the grid.

Climate Capital built the original 2.32 megawatt (MW) solar farm for Junee Prime Lamb in 2023, and now the abattoir is going back for seconds to ensure that it can supply more of its own power needs.

It wants to add another 2.6 MW to the array and a 2.75 MW, two hour battery. 

The abattoir’s biggest energy drawdown period is in the afternoon when butchered meat is chilled after processing, the development application for the extension says. 

“Electricity generated by the solar farm will offset mains power consumption during daylight hours and this will extend into the evening,” it says.

“This period of prime electrical use extends into the evening. The proposed BESS will provide some of the electrical power during the evening period where no solar energy is being generated.

“This will reduce costs for operation of the abattoir and therefore stabilise its viable future in a time where energy costs are causing cost overruns for many industries.”

Commercial-scale solar specialist Climate Capital owns the original $3 million project, which was designed so it could be easily expanded, and sells power back to the abattoir under a 25-year behind-the-meter power purchase agreement (PPA).

It will own the new assets as well. 

Junee Prime Lamb isn’t the only abattoir to supplement its electricity needs with solar and a battery. 

In 2022 Hardwick Meat Works in Kyneton, Victoria, finished its 2.5 MW solar farm, 2 MWh battery and industrial-sized heat pump to offset some of the electricity needed for water heating. 

It expected to save about $508,000 a year from the $2.57 million project.

Local project for a local problem

The new solar farm, which will be to the east of the abattoir and the existing array, will be designed a little differently to a large-scale project. 

For a start, it plans to use 12 blocks of panels in a fixed east-west configuration to capture sunlight in the morning and afternoon, instead of using trackers.

Single and multi-exis trackers tilt panels towards the sun over the course of the day, but can have higher running costs and noise emissions, the planning application notes. 

In fertile rural areas like the Riverina, one of the main objections to solar in particular is that without excellent and early design planning to allow sheep grazing underneath, the land can be lost to production. 

The land that Junee Prime Lamb wants to generate more power was being used for crops and grazing.

But as the development application points out, the dominant land use in that area is a lamb abattoir and the extension will directly support a rural industry directly relating to primary production. Furthermore, it says cleaning up the area of stored and forgotten bits and pieces is likely to improve the local environment. 

If the loss of prime agricultural land is bothersome, so is the heightened traffic movement and noise that comes with building large-scale renewables in the countryside.

Once again, the Junee Prime Lamb site has an advantage given 20-30 large trucks deliver sheep to the abattoir each day. 

“During construction, deliveries to the solar farm is [sic] expected to involve approximately 20-shipping containers of equipment,” the planning application says. 

“On occasion, more than one truck movement may occur on the same day. This will represent less than a 5-percent increase in daily traffic movement to and from the site.”

If you would like to join more than 28,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by
Tags: NSWPlanning

Recent Posts

State utility buys $43 million stake in new big battery, locks in November construction start

State utility helps to bring major new battery project to financial close, in a deal…

17 September 2026

Solar recycler losing “insane amount of money” and about to shed staff as PV pilot program remains suspended

Solar recycling hopeful says it is "losing an insane amount of money" waiting for the…

16 September 2026

The case for plug-in solar and batteries has never been clearer – and renters deserve it

For renters watching rooftop solar spread across the neighbourhood, Australia’s energy transition can feel frustratingly…

16 September 2026

Pacific aid “doesn’t really matter” next to Australia’s fossil fuel subsidies, Tuvalu climate minister says

Since 2020, Australia's subsidies for fossil fuels have totalled almost six times the amount given…

16 September 2026

Labor loses its spine on renewables as premier throws new energy minister, and transition, under the bus

One minute, Victoria's new energy minister was promising industry stakeholders that Labor will hold the…

16 September 2026

First battery modules arrive at biggest storage project to date in Australia’s most renewable grid

First battery units arrive at what will be the biggest storage facility in Australia's most…

16 September 2026