New two-hour big battery soaking up rooftop solar in Brisbane suburbs completes testing process

Published by

The 200MW/400MWh Greenbank Battery project in Logan in south east Queensland has kicked off commercial operations, according to developer CS Energy, including regularly charging and discharging to support market requirements.

Queensland government owned generator CS Energy said on Thursday that the two-hour battery, comprising 108 Tesla Megapack 2XL units, started commercial operations last month in its role soaking up excess solar and boosting the reliability the local grid.

“The battery has gone through a rigorous testing and commissioning process, which was similar to the approach used for the Chinchilla Battery,” said CS Energy chief Brian Gillespie. 

“CS Energy also undertook a detailed operational readiness program, which included employee training, critical risk assessments, and safety and design reviews. 

“Thank you to local residents who attended community updates held by our team during the construction phase. I would like to reaffirm our commitment to being a good neighbour now that we are in the operations phase.” 

Image: CS Energy

CS Energy built the two-hour big battery adjacent to Powerlink’s Greenbank sub-station on the south-side of Brisbane, as part of a “battery blitz” launched in the wake of an explosion at the Callide coal generator back in 2021.

Greenbank is CS Energy’s second grid-scale battery energy storage system (BESS), following the commissioning of its Chinchilla BESS in 2024.

It was the also state’s biggest when first announced, but has since been surpassed by a number of projects, namely Neoen’s 270 MW / 540 MWh Western Downs Battery, which started the energisation process in June of 2024.

A second stage for the Western Downs project, announced in August 2024, will double its size to 540 MW and 1080 MWh.

CS Energy says it worked with Tesla, Consolidated Power Projects, and Powerlink Queensland to deliver the Greenbank Battery. Two experienced “operator maintainers” have been employed in permanent, on-site roles to support operation of the BESS.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australian green hydrogen startup signs deal to deliver its first large-scale electrolyser

An Australian startup promising to transform the economics of green hydrogen has celebrated its fifth…

4 July 2026

Zen Energy put into administration just days after regulatory approvals for sale and transfer

One of the leading lights of a new breed of renewable-energy based utilities placed into…

4 July 2026

Solar Sharer free power offer is being undermined by higher network charges and complex tariffs

Some households will use batteries, EV charging and behaviour change to make very good use…

3 July 2026

China battery giant launches major new push for “circularity” amid EV and home storage boom

China battery giant launches two major initiatives aimed at improving the sustainability of battery manufacturing,…

3 July 2026

Community battery rollout is way behind schedule, with only a quarter built on time

A report into the progress of the federal government's Arena-backed community battery rollout has revealed…

3 July 2026

One of Australia’s first solar and battery hybrid projects reaches financial close, confirming big shift in market

One of Australia's first solar and battery hybrid projects reaches financial close, confirming big shift…

3 July 2026