New 47MW solar farm proposed for Wagga Wagga, home of new Nationals leader

Published by

While we wait to hear what our new deputy prime minister and leader of the National Party thinks of renewables, a new big solar project has been proposed for his home town.

Solar company Green Switch Australia has this week visited the Wagga Wagga suburb of Gregadoo to float its plans to build a 47MW PV farm on grazing land, near the local tip.

Commercial director of Green Switch, Simon Grasby, said the project would cover 91 hectares of land, comprise about 122,000 solar panels, and generate enough energy to power 15,000 households a year.

Grasby said the company hoped to submit their application to the NSW Department of Planning and Environment by April and, if approved, start construction of the solar farm in late 2018.

The plan was to connect to a large substation operated by TransGrid, which Grasby said offered a direct link to the electricity network “to minimise any complications.”

“Our design is quite well advanced and things like our visual impact assessment and noise assessments are all completed, so we’re now talking to the community to get their views,” he said, as reported in the local paper.

The project is one of a number in the development pipeline for Wagga Wagga, which was named as the centre for a potential renewable energy zone in a major report put together by NSW network operator Trasngrid and the Australian Energy Market Operator. (See map above.)

Another 2.5MW project by Global Solar Farms was given the green light last September for development in Bomen.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Firefighter group hits back at “wild claims” and “fear mongering” over transmission lines and fire risk

"Wild claims" that fire fighters will not attend fires on properties hosting new transmission lines…

20 July 2026

Yes, we need more wind power. In the meantime, let’s get the most from the projects we have

Meeting our 82% renewables by 2030 target will take every lever available. Lifting the performance of…

20 July 2026

Should we send data centres into orbit: SpaceX, AI and the Emperor’s new clothes

Can or should data centres be sent into orbit? It might do away with land,…

20 July 2026

Network wars: Ausgrid demands lower transmissions fees as data centres gatecrash the grid

Australia's biggest DNSP is not happy that Transgrid is maxing out its network capacity, and…

20 July 2026

“Important milestone:” Finance landed for AC-coupled big battery to turn operating solar farm into hybrid

Danish renewables developer will add a two-hour big battery to an existing solar farm after…

20 July 2026

Final turbine installed at Australia’s biggest wind farm

Final turbine installed at Australia's biggest wind farm, one of the very few projects that…

20 July 2026