Network wars: Ausgrid demands lower transmissions fees as data centres gatecrash the grid

Published by

The NSW-based Ausgrid is demanding an “imminent reduction” in network charges for all of its New South Wales (NSW) customers, after transmission company Transgrid’s recent humble-brag-warning that data centre connections are maxing out part of its grid.

In June, Transgrid said its Western Sydney network is almost full after it cleared 1.5 gigawatts (GW) of data centres to connect, and said it’s “in advanced discussions” over another 8 GW of prospective load.

The general rule of them is that network costs are fixed and divided by the number of customers. Given the boost in data centres, Ausgrid, which runs the poles and wires that take electricity from transmission lines to homes and businesses, wants to see the benefits of that improved network use now. 

“Our understanding is that these connections are utilising existing capacity and do not require upgrades to the shared transmission network, meaning that they are helping to improve NSW transmission network utilisation,” said Ausgrid executive Mark Ragusa in a letter seen by Renew Economy.

“In this case, Ausgrid expects these connections to lead to an imminent reduction in Transmission Use of System (TUOS) charges for all existing NSW customers.”

Transmission companies saw the benefits of data centre demand early, from more usage of network assets and from the likelihood they will need to build more infrastructure to cater to rising demand. 

Transgrid’s June letter said its existing Western Sydney network will be maxed out by 2033 from the data centre load, and new connections may need to figure out their own grid augmentation.

Talk to us, Ausgrid demands

The race to connect data centres is creating tension between transmission and distribution companies.

Ausgrid is concerned about Transgrid cannibalising grid capacity that it has contracted but isn’t using, and has asked – in no uncertain terms – to be included in large connection planning in future.

“Distribution networks are no longer transmission customers, but peers to be proactively consulted regarding the impact of a large load connections [sic],” Ragusa wrote, highlighting the word ‘customers’ in the letter. 

He said while transmission companies don’t legally have to consult with distributors on network capacity, although the reverse is true for distributors, not doing so “can result in missed opportunities” to figuring out better network usage in the face of huge demand.

It also wants to know exactly how the transmission company came to its conclusions on network availability in June.

“Specifically, we would like to understand how Transgrid’s analysis and forecasts factor in Ausgrid’s authorised demand, as agreed in our Connection Agreement with Transgrid,” Ragusa wrote. 

“We note that, at certain locations across the Sydney basin, Ausgrid is only using a fraction of this authorised demand. 

“Our expectation is that Transgrid, in managing the 8 GW of prospective data centre load in its connections pipeline, has reserved the full amount of capacity needed to meet our authorised demand for the exclusive use of Ausgrid customers.”

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, you can click here to subscribe to our free daily newsletter.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026

Massive wind project, with up to 280 of Australia’s biggest-ever turbines, seeks federal green tick

Plans for a potentially massive new wind farm start federal environmental assessment, proposing up to…

7 August 2026