New 1,660 megawatt-hour battery kicks off commercial operations, including “virtual tolling” deal

Published by

One of the largest four-hour battery projects to be added to Australia’s main grid has announced the start of commercial operations, just weeks after reaching full output on the New South Wales grid.

Melbourne headquartered battery developer Akaysha Energy said on Tuesday that its 415 megawatt (MW) and 1,660 megawatt-hour (MWh) Orana battery energy storage system (BESS), north-east of Wellington, has reached its final development milestone, with the commencement of commercial operations.

The Orana BESS has a virtual tolling agreement (VTA) with big-three utility EnergyAustralia for 200MW of capacity, which will enable the gentailer to notionally ‘charge’ and ‘discharge’ a 200MW ‘virtual battery’ within pre-agreed bidding parameters, independent of the physical operation of the battery.

The big battery was also one of the first, and the biggest at the time, to receive an underwriting agreement from a NSW tender as part of the state’s renewable infrastructure roadmap.

Orana is the third – and so far the biggest – battery project to be completed by Akaysha since it emerged as the surprise winner of a tender to build the country’s most powerful battery – the Waratah Super Battery at the site of the shuttered Munmorah coal fired power station on the NSW central coast.

At the start of the month, Akaysha confirmed that commissioning of Orana was complete, making the BESS visible in the NEM, but had not yet reached commercial operations date (COD).

“COD is a separate milestone and will follow once the final regulatory, market and contractual requirements are completed. We will provide another update when this is reached,” a spokesperson said at the time.

Tony Fullelove, managing director APAC at Akaysha Energy, says the COD milestone for the Orana battery will allow more renewable energy to be integrated into the NSW electricity system.

“The virtual tolling agreement for the Orana BESS gives EnergyAustralia access to the market benefits of large-scale battery storage, including fast-response capacity and greater flexibility,” Fullelove said in a statement on Tuesday.

“Our virtual tolling agreement with Akaysha gives us access to a large-scale battery’s firming capability and the ability to soak up renewable energy that would otherwise be wasted, without owning or operating the asset ourselves,” said Daniel Nugent, trading & transition executive at EnergyAustralia.

“As part of a portfolio mix, it’s a model that helps get batteries financed and built and gets more storage into the market sooner.”

Official commercial operation of the Orana BESS also brings Akaysha Energy’s total operational battery energy storage capacity to over 4 gigawatt-hours (GWh).

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Data centres may be allowed to “build first, catch up later” on renewable mandate, AEMC’s Collyer says

Head of market rule maker says data centres may become "first load that is interruptible"…

12 October 2026

Two new big battery projects name contractors and suppliers as construction gets underway

Two new big battery energy storage systems under development in two states have taken important…

12 October 2026

Fresh delay to contentious Middle Arm gas project prompts call to “cancel it for good”

Middle Arm, a large gas and petrochemical hub earmarked for the NT and which green…

12 October 2026

“We’re building an army:” Angry anti-renewable groups take to city streets ahead of state election

A protest last week brought together a mishmash of causes but its core was opposition…

12 October 2026

Electrification can slash heavy industry bills and emissions – but new report says it will take a team effort

Government-subsidised power for major industries like smelters might not be needed if companies collaborated on…

12 October 2026

The High Court ruling on climate damage | Energy Insiders

Former EDO boss and now Greens MLC Sue Higginson on the huge implications of the…

12 October 2026