Last of 1,038 Wärtsilä Quantum units installed at big battery next to gas plant in coal country

Published by

A four-hour big battery being built in Victoria’s Latrobe Valley to help replace EnergyAustralia’s Yallourn coal power plant, which closes in 2028, has hit a major milestone, with all of its more than 1,000 Wärtsilä battery units now in place.

The 350 megawatt (MW, 1,400 megawatt-hour (MWh) Wooreen Energy Storage System (WESS) is being developed next door to EnergyAustralia’s Jeeralang gas power plant in the heart of Victorian coal country.

EnergyAustralia , one of Australia’s three biggest privately owned utilities, broke ground on the $700,000 million project in February of 2025, hailing it as “the biggest single investment” the company has ever made.

In July, it sold a 50 per cent share in the WESS project to Banpu Energy Australia, the local subsidiary of the Thai energy giant, for about $110 million. EnergyAustralia is still building and operating the project, as well as leading community engagement.

Wooreen is using Wärtsila batteries and smarts, with the balance of plant for project being delivered by Zenviron, which announced the project’s latest milestone on Tuesday.

“The 1,038th and final Wärtsilä Quantum unit was safely delivered and installed recently, marking the completion of all battery installations on the project,” Zenviron said on LinkedIn.

“A fantastic achievement by the entire team, EnergyAustralia and project partners. Thanks to everyone involved for their commitment to safe, efficient and high-quality delivery as we continue progressing this landmark energy storage project.”

The installation of the Wooreen battery next to Jeeralang – a nearly 50-year old gas peaking plant that has an increasingly niche, but still important, role in stabilising the grid – is symbolically significant. The old and the new, side by side.

“It marks the next step in the Latrobe Valley’s energy journey and evolution from legacy coal to becoming a new type of energy powerhouse for our state,” Victorian energy minister Lily D’Ambrosio said at the project’s launch.

The Wooreen battery is scheduled for completion in 2027.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“Scientifically tenuous:” Investors warn half-baked EPBC reforms will leave wind industry in the wilderness

New report warns that some of the draft conditions being explored for the reformed EPBC…

22 July 2026

New solar-battery hybrid promising four hours of storage near Canberra seeks federal green light

The local renewables arm of electronics giant Samsung is seeking a green light from the…

21 July 2026

Who will supply historic gold mining centre’s grid-saving vanadium flow battery?

State government begins evaluating proposals for a 10-hour vanadium flow battery to support the grid…

21 July 2026

“We’re losing time:” Planning delays adding costs and complexity to new renewable projects

Developers say ever increasing planning delays are adding cost and complexity to new wind projects,…

21 July 2026

Solar’s end-of-life problem is not about panel age, it’s about shifting economics and untested plans

Solar decommissioning plans are written into leases and planning consents, but what really determines an…

21 July 2026

The little big battery using local smarts and deeper storage to help fill gap in most renewable grid

Two local companies join forces to help deliver what the world-leading renewables state needs more…

21 July 2026