Nevertire solar farm begins sending power to NSW grid

Published by

The 132MW Nevertire Solar Farm being developed by UK hedge fund subsidiary, Elliott Green Power, has started send power to the grid from its location near Warren, in the state’s north-west.

As you can see in the graph below, supplied by Paul McArdle from Global Roam, the providers of our popular NEM-Watch widget, Nevertire made its first contribution to the NEM at around midday on Sunday, reaching output levels of around 25MW, which will be one of its initial “hold points”.

The project – formerly owned by Epuron – started construction in July of 2018 under EPC contractor Biosar, after reaching financial close in May 2018.

EPG is also the developer of two south-east Queensland projects – the 98MW Susan River and the 78MW Childers solar farms – which it bought from ESCO Pacific in January.

Nevertire is one of many big solar projects set to come online in New South Wales, which has a full to bursting pipeline of PV projects in various stages of the development pipeline.

The state government last month announced the creation of its first renewable energy zone, which aims to facilitate 3,000MW of wind and solar to the market and help replace the state’s ageing coal generators.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“A question of trust:” Net zero chief slams state for falling short on targets despite a lot of talk

Net Zero Commission says Australia's biggest state economy is falling well short of targets, despite…

23 July 2026

Regulator suspends 21 companies in crackdown on false statements over solar and battery installs

Regulator says it has suspended 21 companies from the scheme supporting rooftop PV and home…

23 July 2026

Renewable zone to get major boost in mobile and internet coverage as part of benefits package

State government grants to help telcos upgrade mobile and internet black spots as part of…

23 July 2026

Contract awarded for concrete foundations and early works for ten massive spinning machines

Contracts awarded for concrete foundations and other early works for ten huge spinning machines required…

22 July 2026

Rinehart-backed miner achieves 90 pct renewables in June quarter, may take processing plant off grid

Mine backed by net zero opponent Gina Rinehart achieved 90 per cent renewable share in…

22 July 2026

Network seeks partners on upgrade to nation’s largest isolated grid, to cram in more renewables

State-owned utility seeks expressions of interest for project and contract management partners on its massive…

22 July 2026