Utilities

“Logjam of loads:” Network says data centre rush will push some parts of grid to capacity by 2033

Published by

Transgrid’s network in western Sydney will be largely full by 2033 thanks to the huge influx of data centres, the grid operator has told connection applicants. 

The 330 kilovolt network in the area is already nearly full after the network signed contracts to connect 1.5 gigawatts of new data centres.

The “unprecedented increase” in enquiries around large-scale electricity loads in Western Sydney is a major change from historical, predictable demand patterns, Transgrid said in a letter in mid-June.

“Data centre demand is now at significant scale and pace, with enquiries concentrated towards Western Sydney,” it said.

“More than 8 GW of prospective data centre load is currently in advanced discussions with Transgrid regarding potential connection to the transmission network. To put that into perspective, the average daily demand for electricity in New South Wales (NSW) typically ranges between 7.5 GW and 10 GW.”

And while that 1.5 GW can be accommodated within the current network, future connections are likely to be constrained. 

The news of Transgrid’s capacity difficulties was revealed by Infraseek on LinkedIn this week, in a post that noted that the significance reaches well past western Sydney. 

“The NEM’s open access framework for connections was devised in an era of large central generation and the connection of smaller, more consistent loads,” the post says.

“Current NEM Rules provide little philosophy on how a finite amount of capacity should be shared once gigawatt-scale loads begin arriving together. 

“The data centre development sector, progressing projects at both transmission and distribution levels, has no independent view of how much network capacity remains or how it is being allocated. 

“The logjam of loads building up around Sydney is reminiscent of the pile-up of generation in north-west Victoria a few years ago, the so-called ‘Rhombus of Regret’. Will we see a ‘Polygon of Pain’ emerge in Western Sydney as data centre development runs ahead of network capacity?”

Infraseek says networks in other countries are already struggling with the issue, with the likes of PJM, the biggest grid operator in the US, and Texas’ ERCOT, as well as others in Finland, the UK and Ireland now putting structures in place to manage demand.

“[They are] all moving to manage oversubscribed connection queues and tighten fault ride-through rules for large loads, ranging from Ireland’s multi-year moratorium on new Dublin data centres to Great Britain’s readiness-based queue reform and ERCOT’s new ‘Batch’ studies,” the post said. 

Transgrid says data centres may be able to join the constrained western Sydney grid, but will need to pay upfront for network augmentations if they want to connect, because there is “limited scope” to accommodate them now. 

“Transmission network augmentations need to be funded upfront by prospective data centre proponents that either trigger the need or are expected to benefit from the additional capacity, regardless of whether they are seeking to connect to Transgrid’s network or a distribution network,” the grid operator said in its letter. 

“We note that application of this principle to proponents connecting at the distribution level is subject to anticipated regulatory change.”

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by
Tags: NSWTransgrid

Recent Posts

Origin wants to supersize the Eraring battery to make it easily the biggest in the country

Origin Energy seeks approval for new addition to its Eraring battery that would take the…

5 October 2026

Going full hybrid: Massive, $2 billion solar and battery proposed at site of newly expanded wind farm

More projects are going hybrid: A $2 billion solar and battery addition is proposed to…

5 October 2026

Where’s Evo? The missing network in Canberra’s bold electrification experiment

Canberra is becoming a real-world laboratory for mass electrification, but its local electricity network will…

5 October 2026

Not a “dealbreaker:” Big Victorian wind project doesn’t need VNI West

The Macorna wind project will have a simpler ride through state planning, and insists it…

4 October 2026

Huge 195-tonne transformer arrives at big battery site after 1,300 km road trip

One of the heaviest and longest road trips ever undertaken in Australia's energy transition has…

4 October 2026

Australia is making big bets on a slow transition, but the technology S-curve tells a different story

Australia has a choice between investing in the future we can already see – or subsidising…

4 October 2026