More contractors have been stung by the costs of connection delays for renewable energy projects, with the listed developer Infigen Energy disclosing that it received more than $10 million of “compensated revenue” from delays at the Bodangora wind farm in NSW.

Details of the issue are scant, and Infigen has declined to comment further. It said in a brief statement accompanying its latest production and revenue figures that it had received $10.1 million of compensated revenue.

It said this was “primarily relating to liquidated damages for construction delays at Bodangora Wind Farm.”

The 113.2MW Bodangora facility started production a year ago, after work on the site began in June, 2017. The EPC contractors were named in Infigen press releases at the time as Civil and Allied Technical Construction Pty Ltd (CATCON) and General Electric International Inc. (GE) which manufactured and supplied the turbines.

The overhead powerlines connecting the wind farm to the electricity grid have been built by TransGrid.

Bodangora is just the latest in a long and growing line of wind and solar farms that have experienced delays in connection and commissioning, and which have resulted in “compensated revenue”, or “liquidated damages” and which in some cases has taken a heavy toll on contractors.

RCR Tomlinson collapsed under the weight of cost over-runs, damages claims and cash flow delays as the result of problems at nearly one dozen solar farms it was working on, while Downer Group, Bouyges, Tempo Australia and others have also been hit by damages claims or cost over-runs.

In Queensland, Adani Renewables’ Rugby Run solar farm was only connected more than six months after the solar farm’s machinery was in place, and an even longer delay affected the world-leading wind-solar-battery complex at Windlab’s Kennedy Energy Hub.

The problems have been variously blamed on the sheer number of projects seeking to connect at the same time, tight new connection rules, last minute alterations, the lack of preparedness by some developers and contractors, and the lack of resources in network companies.

Some contractors, such as Tempo, have sought to renegotiate contracts, avoiding the threat of liquidate damages, while there is a growing debate about who should take responsibility for connection delays, the developer or the contractor.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

“Self-erecting” wind turbine hits power milestone ahead of joining Fortescue Pilbara project

A prototype wind turbine using "self-erecting" tower technology is running at full capacity, ahead of…

26 March 2026

Another big battery prepares to power up as Sunshine state leads extraordinary charge to storage in 2026

Battery component of solar and storage facility joins the grid, part of a boom that…

26 March 2026

Fusion power plant possible by 2045 with massive effort, says science academy

Germany wants to build the world's first fusion power plant, and scientists say that might…

26 March 2026

Big spinning machines: State seeks partners for syncon rollout at former coal hub

Government seeks expressions of interest to partner in delivering at least three new synchronous condensers…

26 March 2026

A home battery case study: From little interest in storage, to bills that are always in credit

Until recently, I had little interest in purchasing a household battery. I am now one…

26 March 2026

Fake news on everything from whales to wind farms: Australia’s climate misinformation tsunami

Senate inquiry uncovers countless instances where misinformation – and often disinformation – is affecting public…

26 March 2026