“Mind boggling:” World’s largest offshore wind farm powers up, with lessons for Australia

Published by

The first fully operational turbine at the world’s largest offshore wind farm, the 3.6GW Dogger Bank project in UK waters, has started sending power to the British grid.

Local press reported that developers had confirmed the milestone on Monday, with one of GE Vernova’s massive Haliade-X 13MW turbines – the first of 277 – connected to the electricity grid over the weekend.

The project, jointly developed by Britain’s SSE and Norway’s Equinor and Vårgrønn, is being developed off the coast of Yorkshire in three 1.2GW phases: Dogger Bank A, B and C.

Developers say each rotation of the 107-metre-long blades on Dogger Bank’s first turbine could produce enough energy to power the average British home for two days.

Alistair Phillips-Davies, chief executive of SSE, said the development of offshore wind was “exactly how” the UK should be responding to the global energy crisis and to climate change.

“Dogger Bank will provide a significant boost to UK energy security, affordability and leadership in tackling climate change,” he said.

“[This is] a landmark moment for the global offshore wind industry … demonstrating just what can be achieved when policymakers, investors, industry, and communities work together to achieve something truly remarkable.”

Stretching the sinews of of technology

The production of first power from Dogger Bank – albeit, from just one turbine – is a welcome sign of progress for the offshore wind sector at a time when much of the news has revolved around soaring project prices and abandoned contracts.

It also offers a window into the future for Australia, where one of the Dogger Bank developers is proposing a similarly sized project for the Gippsland development zone off the coast of Victoria.

In Australia, SSE has teamed with Singapore-based and Australian managed Equis Developments to apply for one of the feasibility licences being offered in the Gippsland zone, to build a 3.5GW project in a “target area” of around 700 sq kilometres.

Dan Pearson, the director of business development at SSE, told RenewEconomy in a recent interview that the project the company was proposing for Australia had a lot of similarities to Dogger Bank, including the project size, the water depths and seabed conditions.

“That was one of the reasons for choosing that site,” Pearson said via video call from the UK.

“The way that we develop projects is we will look for the lowest cost of energy. So that’s our main driver.  …And so obviously, at certain sites you have better wind speeds and better [water depths].

“The site that we’ve chosen [in Victoria] plays to our strengths,” he added.

“We are… stretching the technology boundaries with Dogger and, you know, without wanting to pour cold water on any of our competitors, they would have to … go up that learning curve to be able to deliver the same sort of project.”

Pearson says the engineering that’s gone into Dogger Bank has been “mind boggling,” but adds that the project – despite its size and complexity – has had a “pretty smooth ride” to development so far.

“We are stretching the sinews of the edge of technology here but so far, so good. We’re very happy how progress has been.”

And he says the investment philosophy for offshore wind is still sound, despite reports of rising costs and supply chain pinch points.

“I think we’re at a bit of an inflection point, whereby I think the supply chain is now biting back, saying, ‘look,  you developers have been pushing us really hard over the past decade. We’ve been designing turbines to be able to suit your levelised cost of energy requirements… We now need to take a breath.

“‘We would like to keep these turbines as they are, build up reliability and actually start making some money on the turbines’.

“We still feel that this is a very cost competitive technology that with the right mechanisms can really deliver on the net-zero agenda … And actually, to be honest, I think the government has to rely on it because. … there aren’t that many other avenues for them.”

Pearson says SSE is comfortable with policy approach that the Albanese government is taking for projects, including the current process of bidding for a seabed licence. “We are very familiar with it and comfortable with developer risk,” he says.

And he says the biggest concern for developers hoping to build offshore wind in Australia is that the transmission will be ready to connect the projects to the grid. But well before that, the most important task ahead is community engagement.

“It’s everything,” he told RenewEconomy. “If you don’t have the locals with you, if you don’t have the region with you … then things go south very quickly.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australia’s most powerful battery set free of massive “shock absorber” contract after delay to Eraring coal closure

Australia's most powerful battery now free to trade its full capacity on market after its…

10 October 2026

Look, no turbines! Natural landscape returns at site of decommissioned wind farm

The site of one of Australia's very first wind farms now shows little evidence of…

10 October 2026

Kudos where it’s due: Australia’s quiet role electrifying the rallying cry for the COP we never got to host

The "35 by 35" electrification goal has an Australian origin that the government seems to…

9 October 2026

The Queensland LNP plan for coal-powered data centres could cost taxpayers $20 billion a pop

If we fail to ensure data centres pay for new renewables and storage to cover…

9 October 2026

Home batteries and time-of-use tariffs may be best combination to steer households away from evening peaks

Home batteries look like resetting the behaviour of households when it comes to responding to…

9 October 2026

South Australia won’t reach its 100 pct net renewables target on schedule, but it won’t be the fault of households

South Australia energy minister hints that the 100 pct net renewables target may not be…

9 October 2026