The final foundation has been poured at the Rye Park Wind Farm in New South Wales, with 66 concrete foundations poured over the last 10 months set to play host to 6MW wind turbines.

Leading Australian renewable energy developer Tilt Renewables announced on its LinkedIn page that the final foundation had been poured late last week.

Construction partner Zenviron and subcontractors have been pouring foundations since July last year. A total of 66 foundations have now been poured, each of which will play host to a 6MW wind turbine – the largest wind turbine to be used so far in Australia.

The first Vestas V162 6.0MW turbine was installed at Rye Park earlier this year, at which point only 37 of the foundations had been poured. Tilt Renewables expects the wind farm to begin full operations in the middle of 2024. It is contracted to supply power to the Cadia gold mine owned by Newcrest.

Rye Park is one of Australia’s larger wind projects, and the biggest to date in NSW, and reached financial close in the middle of 2021 and began construction later that year, at which point it was also announced that the project would utilise the Vestas V162 6.0MW turbines.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

“Fewer people calling on coal:” Suburban hotspots revealed as home battery rebates top 200,000

Home battery rebates have already topped 200,000, and heading to two million by 2030, with…

17 January 2026

Home battery installations will match the scale of Snowy Hydro scheme – in a single year

Household battery numbers continue to defy all predictions, and they now look set to match…

16 January 2026

“Too valuable to throw out:” Labor announces first national solar panel recycling pilot program

Federal government announces $25 million for a rooftop solar recycling pilot, with up to 100…

16 January 2026

Fortescue begins work on first wind farm, with self-lifting towers and Australia’s biggest turbines

Andrew Forrest's Fortescue starts construction of its first wind farm, featuring unique "self-lifting" tower technology…

16 January 2026

Standalone battery proposed for old gravel pit gets final planning tick despite long distance objectors

A $200 million standalone battery project that attracted no objections from within 50kms of the…

16 January 2026

Australia’s climate hit regions will need fit-for-future science and modelling

It won’t come as much consolation to Victorian communities picking through the burnt rubble from…

16 January 2026