Construction of the largest and most complex substation in the Southern Hemisphere has been completed in south west New South Wales, part of Project EnergyConnect, the new transmission line linking South Australia, the country’s most advanced renewable energy state, to NSW, with the biggest coal fleet.

The Buronga substation will act as the main hub for Project EnergyConnect’s connection between NSW, Victoria, and South Australia and will anchor the new 900-kilometre transmission line to connect the energy grids of all three states.

“EnergyConnect is critical to improving the reliability and security of the National Electricity Market as coal-fired power stations retire, with interconnections to boost energy sharing between NSW, South Australia and Victoria,” said Gordon Taylor, executive general manager of major projects for Transgrid.

The substation has been steadily energised over the past four weeks, with the final section completed last week. Once the final 540km section of the EnergyConnect transmission line is completed between Buronga and Wagga Wagga, it will increase capacity at the substation from 150 megawatts (MW) to 800 MW.

Taylor says the Buronga substation is the first in the world to boast five phase-shifting transformers running in parallel, which provides improved load sharing, increased grid stability, enhanced transmission capacity, and reduced congestion.

“(It) is a true feat in design, engineering, construction, and commissioning,” he said.

The substation covers 15 hectares – equivalent to 21 soccer fields – and comprises 24,000-cubic-metres of concrete and a host of sophisticated electrical equipment included synchronous condensers, phaseshifting transformers, shunt reactors, step down transformers, power transformers, and capacitor banks.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Bowen launches review of emission caps and credits for Australia’s biggest carbon polluters

Policy review will investigate settings for Australia's 2030 and 2035 emissions reduction targets.

7 August 2026

Energy Insiders Podcast: Will data centres make or break wind?

Kane Thornton has moved from the peak renewables body to data centres, now the presumed…

7 August 2026

Climate Active is dead. The funeral will not be certified carbon neutral

Australia's government-run "carbon neutral" certification scheme is being wound up. It is good news for…

7 August 2026

Australia’s first offshore wind auction is “going ahead as planned,” new energy minister confirms

Victoria's newly appointed energy minister says the state will go ahead as planned with Australia's…

7 August 2026

Labor’s data centre gas double-speak leaves the gate open for dodgy offsets

A promise of banning gas while waving through “gas firming” and “gas peaking” with unlimited offsets leaves…

7 August 2026

Massive wind project, with up to 280 of Australia’s biggest-ever turbines, seeks federal green tick

Plans for a potentially massive new wind farm start federal environmental assessment, proposing up to…

7 August 2026