Wind

“Largest ever” turbine blades en route to Australia’s largest wind farm

Published by

Construction is underway on what will be – at least for a time – Australia’s largest wind farm.

Project developer AGL Energy said on Friday that the foundations had been laid at the site of the 453MW Coopers Gap Wind Farm in Queensland, and parts of the massive turbines were making their journey from port to site, around 180km north of Brisbane.

And when we say massive, we mean massive – as in, the largest wind turbine blades ever transported in Australia.

That’s according to AGL, who said a trial delivery of the blades and other components had been successfully completed on Tuesday, in preparation for “sustained overnight deliveries” for the rest of the year.

AGL Project Manager, Tim Knill, says the largest turbine blades measure 67.2 metres long and weigh in at a hefty 22 tonnes.

“Several shipments of wind farm components, including the blades, have arrived at the Port of Brisbane and are in storage awaiting transportation,”  Knill said.

“The movement of such large pieces of equipment requires detailed planning and we are predicting approximately 1,200 oversize movements, involving blades, hubs, tower sections and nacelles,” he said.

“We aim to minimise the impacts on commuters so many of the movements are done at night time.”

Knill says the increased level of complexity of transporting the extra long blades is compensated for by the fact that, once installed, they allow more energy to be captured by every turbine, thus bringing down the cost of generation.

On that matter, Coopers Gap has already impressed, having secured – in August last year – an off-take price of below $60/MWh for energy generated by the south-east Queensland wind farm.

The deal included AGL writing a PPA for electricity and associated renewable energy certificates of less than $60/MWh for an initial five years, with an option to extend the agreement for another five years at the same – or even lower – price.

Once completed – it’s expected to be operational by mid-2019 — the project will comprise a total of 123 wind turbines, with 91 x 3.63MW turbines (137m rotor diameter) and 32 x 3.83MW (130m rotor diameter) turbines.

“The wind turbines will have a tip height of 180 metres. The hub height (axis or rotation) will be 110 metres (3.6MW – 137) or 115 metres (3.8MW – 130),” said Knill.

“The total capacity of the wind farm will be 453MW making it the largest wind farm by MW capacity in Australia.

“It’s estimated around $56 million will be spent by the project on services provided by local businesses during the construction phase… with 20 ongoing jobs created on site to maintain and operate the turbines.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Swiss commodity trader gets approval to buy Zen retail business and PPA deals. Will it take on Big 3?

One of the world's biggest commodity traders moves into Australia electricity retail business - competition…

26 June 2026

Judge dismisses legal bid to prevent gas fracking in the Top End

Activists have lost their court bid to prevent gas exploration in the Northern Territory after…

26 June 2026

Nuclear reactors taken offline in France, as extreme heat pushes river temperatures into danger zone

EDF has taken nearly 10% of its nuclear power capacity offline this week, to avoid…

26 June 2026

South Australia swings from three days of 100 pct renewables to worst drought in 7 years

South Australia just experienced its worst wind drought in seven years. The fleet of short-duration…

26 June 2026

“Not consulted:” Local councils in the dark on LNP plan to “scrap” huge renewable zone and “evaporate” benefits

Local government leaders say they were in the dark over state Coalition plans to revise…

26 June 2026

Solar Insiders Podcast: Virtual networks and the real pursuit of energy democracy

Deakin University's Andrea La Nauze on the early findings from an Australia-first trial of technology…

26 June 2026