First turbines up and spinning at Australia’s largest wind farm

Published by

Some of the massive turbine blades that started making their way to the 453MW Coopers Gap Wind Farm in Queensland in September are now up and and ready to spin, after the completion of the first wind towers at the site north of Brisbane.

Project developer AGL Energy said the first of 123 turbines that will make up Australia’s largest wind farm – at least for a time – was being completed in mid-November, marking “a great milestone” for Coopers Gap.

“Projects like this involve enormous efforts by many stakeholders; the logistics of getting the massive components to site alone is one of the areas which can prove challenging,” said general manager of development and construction, Dave Johnson.

“We have worked with many government agencies and others to have the components transported from the Brisbane Port to our site for what will be a 453MW power station.”

As we reported here in September, delivery of the blades – which AGL claims to be Australia’s largest – was no easy feat, with the largest measuring 67.2 metres long and weighing in at a hefty 22 tonnes.

Johnson said this week that on-site construction of the wind farm was progressing well, with 95 foundations poured, both main transformers energised, construction of the 275kV substation by Powerlink complete, and energisation of the 33kV switchyard expected next week.

The wind farm is on track to be completed in late 2019.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Swiss commodity trader gets approval to buy Zen retail business and PPA deals. Will it take on Big 3?

One of the world's biggest commodity traders moves into Australia electricity retail business - competition…

26 June 2026

Judge dismisses legal bid to prevent gas fracking in the Top End

Activists have lost their court bid to prevent gas exploration in the Northern Territory after…

26 June 2026

Nuclear reactors taken offline in France, as extreme heat pushes river temperatures into danger zone

EDF has taken nearly 10% of its nuclear power capacity offline this week, to avoid…

26 June 2026

South Australia swings from three days of 100 pct renewables to worst drought in 7 years

South Australia just experienced its worst wind drought in seven years. The fleet of short-duration…

26 June 2026

“Not consulted:” Local councils in the dark on LNP plan to “scrap” huge renewable zone and “evaporate” benefits

Local government leaders say they were in the dark over state Coalition plans to revise…

26 June 2026

Solar Insiders Podcast: Virtual networks and the real pursuit of energy democracy

Deakin University's Andrea La Nauze on the early findings from an Australia-first trial of technology…

26 June 2026