Qld solar-paired pumped hydro plant could reach 450MW

Published by

A pumped storage hydropower project that is proposed for north Queensland, to be built alongside what could be Australia’s largest solar farm, could be much bigger than first conceived, with new designs suggesting peak generation capacity at a maximum of 450MW over a 5-6 hour period.

The Kidston Pumped Storage Hydropower Project is being developed at the disused Kidston Gold Mine in north Queensland and is currently at the feasibility study phase, which has been supported by the Australian Renewable Energy Agency (ARENA).

The “world first” project – which is being developed by NSW-based Genex Power – aims to transform two adjacent pits left over from the disused mine into a large-scale hydroelectric power plant, that will store excess generation from a 150MW solar array, and then sell it to the grid at times of peak demand.

Pumped storage hydropower – there are currently only three examples of this in Australia – is a highly efficient form of large-scale energy storage that would pair well with the introduction of more wind and solar power into the NEM.

It has the potential to generate rapid response, flexible power for delivery into the National Electricity Market (NEM).

Genex said last week that power and water consulting firm Entura, along with project partner HydroChina, had produced a new design (see image above) with the potential to increase the plant’s head and peaking generation capacity, beating earlier expectations.

In a statement to the ASX on Thursday, Genex said the design layout of the Project had evolved substantially since the pre-feasibility study (PFS) concept was initially identified.

The new “optimal” design proposes a “Turkey’s Nest” shallow dam design for the upper reservoir, which would incorporate a number of strategic advantages, and remove a number of previous constraints.

“Most significantly,” the ASX report says, the design enables a significant increase in the installed capacity of the project, from the initial 330 MW to up to 450MW.

“Clever thinking and commercial focus has delivered an optimal design solution to maximise the potential of our project,” said Genex managing director Michael Addison.

“The new design provides the lowest cost per MW of installed capacity and presents the lowest operating and environmental risk.”

Project Director and Principal Consultant, Civil Engineering at Entura, Richard Herweynen, said significant studies and investigations have been undertaken over the past months to provide confidence around this solution.

“Our new design, which provides for a low turkey’s nest dam design for the upper reservoir located on the top of an old waste rock dump, was developed through a detailed options assessment and optimisation process,” he explained.

Entura has worked with clients in more than 30 countries over the past few decades – including India, Laos, Malaysia, Papua New Guinea, South Africa and Tajikistan – assisting with developing, operating and maintaining hydropower assets of all sizes.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Australian green hydrogen startup signs deal to deliver its first large-scale electrolyser

An Australian startup promising to transform the economics of green hydrogen has celebrated its fifth…

4 July 2026

Zen Energy put into administration just days after regulatory approvals for sale and transfer

One of the leading lights of a new breed of renewable-energy based utilities placed into…

4 July 2026

Solar Sharer free power offer is being undermined by higher network charges and complex tariffs

Some households will use batteries, EV charging and behaviour change to make very good use…

3 July 2026

China battery giant launches major new push for “circularity” amid EV and home storage boom

China battery giant launches two major initiatives aimed at improving the sustainability of battery manufacturing,…

3 July 2026

Community battery rollout is way behind schedule, with only a quarter built on time

A report into the progress of the federal government's Arena-backed community battery rollout has revealed…

3 July 2026

One of Australia’s first solar and battery hybrid projects reaches financial close, confirming big shift in market

One of Australia's first solar and battery hybrid projects reaches financial close, confirming big shift…

3 July 2026