Kidston pumped hydro project gets $147m state government boost

Published by

The Queensland government has confirmed that it will provide $147 million in funding towards a new transmission network link to Genex’s Kidston pumped hydro project.

Genex is developing a 250MW/2,500MWh pumped hydro storage project at the site of two disused gold mining pits in Kidston in Queensland, which will require a new 186km transmission infrastructure link to connect the project to the main grid.

Genex is aiming to establish the project as part of a new clean energy hub, with plans to co-locate wind and solar projects around the pumped hydro facility.

As a key milestone for the project, the Queensland government confirmed that it would provide $147 million in funding towards the cost of new network infrastructure – a $15 million increase from its preliminary commitment.

The funding package includes the construction of a new 275kV transmission line between Kidston and Mt Fox and the installation of a new substation at Mt Fox.

The link will be developed by Powerlink, which will receive the funding directly, and should provide sufficient connection capacity to facilitate the creation of a new renewable energy zone in North Queensland.

Genex CEO James Harding said the funding commitment was an important step forward, as the company approaches financial close on the pumped hydro project.

“This funding is a crucial piece for the overall project financing for the project, which is rapidly advancing toward financial close. We will continue to update the market as we move through the final approvals and documentation in the coming weeks,” Harding said.

“The Transmission Line will support not only our flagship Kidston Pumped Storage Hydro Project, but the broader Kidston Clean Energy Hub including the Kidston Stage 3 Wind Project and the Kidston Stage 2 Solar Project, with the creation of a new North Queensland Renewable Energy Zone.”

The Queensland funding commitment had been first flagged in 2019. Genex has been close to finalising partnership agreements for the Kidston pumped hydro projects for some time, but has faced delays as the company works out the final arrangements for each deal.

EnergyAustralia is set to serve as the main energy off-taker for the project, while the Northern Australia Infrastructure Facility has been lined up to provide a $610 million loan to finance the construction of the storage project. Japanese utility J-Power has also worked with Genex as an equity partner in the project.

Michael Mazengarb is a Sydney-based reporter with RenewEconomy, writing on climate change, clean energy, electric vehicles and politics. Before joining RenewEconomy, Michael worked in climate and energy policy for more than a decade.
Michael Mazengarb

Michael Mazengarb is a Sydney-based reporter with RenewEconomy, writing on climate change, clean energy, electric vehicles and politics. Before joining RenewEconomy, Michael worked in climate and energy policy for more than a decade.

Share
Published by

Recent Posts

Five ways to save Capacity Investment Scheme from attack by zombies

CIS structure needs to minimise risks of zombie projects, and reward bidders with projects they…

19 April 2024

First of 2,600 battery units arrive for installation at Australia’s biggest grid “shock absorber”

The first shipment of 2,600 battery units for the giant Waratah Super Battery have arrived…

19 April 2024

EV fast charger pioneer Tritium calls in administrators after declaring itself to be insolvent

Australian EV fast charger maker Tritium, once valued at $2 billion, calls in administrators after…

19 April 2024

BHP chooses fast start gas over long duration storage to support wind and solar for huge Pilbara mines

BHP chooses to add fast start gas generators to Pilbara grid, rather than long duration…

18 April 2024

Victoria bans gas rebates and incentives for homes as shift to all-electric gathers pace

Victoria bans fossil gas companies from offering cash incentives or rebates to households that install…

18 April 2024

Solar Insiders Podcast: Australia loses it on solar

Australia falls out of global top 10 solar countries. Plus: GridBeyond's Michael Phelan on the…

18 April 2024