Storage

Genex to add more solar and wind to pumped hydro after Queensland funds new link

Published by

Genex Power’s landmark Kidston Pumped Hydro project has received a major boost, with the Queensland government pledging to tip $132 million into construction of a transmission line, linking the renewables hub with the main grid.

In a statement on Wednesday, the Palaszczuk government said Powerlink would build a 186km single circuit line from the Kidston project to Mount Fox near Ingham, linking the hinterland to the National Electricity Market.

It’s a crucial step forward for the world-leading project, which will co-locate the 250MW pumped hydro facility, with about eight hours of storage, with an existing 50MW solar farm and a planned second stage 270MW solar farm.

In its own statement on Wednesday, Genex welcomed the “significant” funding package as a “key external” ingredient to complete financing and commence construction of the Kidston Pumped Storage Hydro Project Transmission Line.

Genex CEO James Harding said the state government support it would also help unlock further stages for the Kidston Clean Energy Hub, including the additional 270MW of solar and up to 150MW of wind.

For the state-owned Powerlink, the Kidston pumped hydro storage will make a welcome addition to the rapidly changing grid.

“Connecting 250MW of pumped hydro capacity will help make the North Queensland electricity network more reliable,” said state energy minister Anthony Lynham in comments on Wednesday.

“Building this breakthrough 186 kilometre transmission line and associated infrastructure will create 400 jobs over two years,” he said.

“The Genex project itself will have a peak construction workforce of about 500 people per annum for the first two years, 250 in the final year and 30 permanent operational jobs.

Deputy Premier and Treasurer Jackie Trad took the opportunity to take a swipe at the federal Coalition – although the federal government’s Northern Australia Infrastructure Facility has previously committed $610 million of “concessional finance” for Kidston.

“In the absence of a federal energy policy, Queensland is once again doing the heavy lifting by backing projects like Genex at Kidston,” Trad said.

“The evidence from the market is clear – industry sees the benefits of renewable energy and is putting its money on the table.

“What’s needed now is the means to connect these emission-free projects to the grid and get the power to where it’s needed.”

Genex’s Harding said the Queensland government funding package complemented the project loan extended by the NAIF.

“We would like to thank the Queensland government for their support and look forward to continuing to work together over the coming weeks to finalise arrangements for this important increment to a stable electricity network in North Queensland, which will secure power supply to local communities and unlock further clean energy generation in the region,” he said.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Councils call for national climate compensation fund – and they want the polluters to pay

Local governments want a national fund to help pay for the soaring costs of climate…

19 June 2026

Burning forest “waste” to make cement is poor climate policy, poor environmental policy and bad economics

The Australian government has agreed to invest almost $53 million to help upgrade a coal-fired kiln to…

19 June 2026

Delaying clean energy is what really makes power bills soar

What is making us poorer is not the move to clean energy – it is…

19 June 2026

Energy Insiders Podcast: The problem with network tariffs

AEMC chair Anna Collyer discusses the pricing review, network tariffs, and the right of monopolies…

19 June 2026

“Great green incinerator:” Hanson channels Rinehart attacks on wind and solar, but it’s not all it seems

Gina Rinehart and her political protege Pauline Hanson launch new attack on wind and solar,…

19 June 2026

Big battery blitz: Six-hour giant with 4.8 GWh of storage approved as 8-hour project joins queue

One of the biggest isolated grids in the world continues to flex its energy storage…

19 June 2026