The Equation
After a very slow start in 2013, US wind development is really starting to pick up. According to the American Wind Energy Association’s (AWEA’s) just released Third Quarter 2013 Market Report, over 7,500 megawatts (MW) of new wind power capacity is under development in the US, representing an investment in the U.S. economy of roughly $15 billion. This is good news considering that only 1.6 MW was installed in the first two quarters of 2013, and only 68 MW in the third quarter. After installing a record 13,100 MW of wind capacity in 2012, the slow pace of development in the first nine months of the year can be attributed to the late extension of the federal Production Tax Credit (PTC), a few days after it officially expired at the end of last year (see more details here).
Other key highlights from the report:
In addition to taking advantage of the PTC before it expires (again), utilities are also seeing very favorable pricing for new wind projects. Project data from the U.S. Department of Energy’s 2012 Wind Technologies Market Report show that PPA prices have fallen from a U.S. average of nearly $70/MWh in 2009 to below $40/MWh in 2012 — a whopping 43 percent decline over a 3-year period.
These reductions in PPA prices are largely due to reductions in capital costs and increases in capacity factors resulting from taller towers and new wind turbine designs. In 2012, PPA prices ranged from about $20/MWh to $80/MWh, with the lowest prices in the Plains states and higher than average prices in the West, Northeast, Great Lakes, and Southeast states (see figure below). Many wind projects in this price range are competitive with, and even less expensive than, new natural gas plants.
Source: Wiser, R. and M. Bolinger. 2012 Wind Technologies Market Report. U.S. Department of Energy.
Utilities are clearly taking notice, as my colleague Mike Jacobs noted, and are even using wind as a hedge against future increases in natural gas prices. For example:
Along with economics, policy is another important driver, and clarity about the policy is equally important. The IRS released guidance on PTC eligibility on April 15, and again on September 20, to give developers and utilities more clarity on how to move forward with projects. Under the new rules, projects do not have to be completed and operating by the end of the year to qualify. Instead, they have to be under construction and meet certain milestones and criteria, such as spending at least 5 percent of the project costs before the end of 2013. This gives developers and utilities a little more wiggle room to complete projects compared to the old rules that had a strict December 31 deadline.
State renewable electricity standards (RESs) also continue to be an important driver for wind development. While utilities in most states have enough renewable generation to comply with their current standards, many utilities are planning ahead to meet future requirements to take advantage of the PTC and recent wind turbine cost reductions.
Australia's biggest operating wind farm has set a stunning new record, becoming the first in…
The passive battery is not a new phenomenon. What is new is that its value…
State-owned utility says it is in discussions to invest in non-lithium technologies with up to…
Batteries have been protecting consumers from price spikes in most states over summer. But they…
State Electricity Commission CEO Chris Miller on how the government-owned energy company is filling gaps…
Australia’s electricity prices ignore location, even though the grid doesn’t. This mismatch drives congestion, curtailment,…