Storage

Genex secures new finance to shore up pumped hydro and fund big battery plans

Published by

Genex Power has announced a major new funding deal to bring home its flagship pumped hydro project at Kidston in Far North Queensland and drive development of the massive up to 2GW Bulli Creek solar and battery project.

The $44.5 million funding package was announced on Friday by Genex and J-Power, the Japanese utilities giant that has been collaborating with Genex on the Kidston Clean Energy Hub since 2020, including through a previous $25 million investment commitment for K2-Hydro.

This time around, J-Power has agreed to provide a loan facility of $35 million as additional standby source of funding for the 250MW, eight hour storage (2,000MWh) pumped hydro project, to help ensure it remains on track for energisation in 2024.

The hope is that the standby funds will not be needed, but Genex says that – following a September 2022 drilling incident that caused a water ingress and “modest delays” to works – they will act as “a significant buffer” to any further bumps in the road.

“While the costs of the water ingress event … have been fully funded, we consider it prudent that additional funding is secured against any further unforeseen events during the balance of the construction program,” Genex CEO James Harding said on Friday.

On top of the loan facility, J-Power will also establish a joint development fund for Genex’s up to 2GW of battery storage and solar capacity at the Bulli Creek project in Queensland’s Toowoomba region, where it plans first to build a 400MW battery with two hours of storage.

The joint development agreement gives J-Power a 50% interest in Bulli Creek, through upfront acquisition funding of $2.5 million, and a further $6 million in upfront funding for third party development costs and $1 million to cover early costs of the project.

Ongoing third party development costs for Bulli Creek will then be funded by both companies on a 50:50 basis, extending the strategic partnership initiated via co-development of the 258MW Kidston Stage 3 wind project.

The facility is secured against Genex’s equity interests in Bulli Creek and the Kidston wind farm.

“This funding will be instrumental in fuelling the growth of our renewable energy portfolio in Australia,” says Harding, who hands over the reins as CEO of Genex in Spring, to current CFO Craig Francis.

“The loan facility with J-Power gives us significant buffer to complete the construction of the [Kidston pumped hydro] project.

“In addition … the Joint Development Agreement for the Bulli Creek Project will allow us to fast-track development activities at this exciting project, which represents the next phase in the company’s growth.”

Earlier this week, Genex began energisation of its first energy storage facility, a 50MW/100MWh Tesla big battery  in Bouldercombe near Rockhampton in Queensland – a project it says has been built on time and on budget.

Energisation of the Bouldercombe battery marks the final milestone before a lengthy commissioning process which is set to be complete by October, in time for Queensland’s summer demand peaks.

As RenewEconomy has reported, this is a big deal for Genex, with the Bouldercombe BESS – only the second large-scale energy storage system to be installed in the Sunshine State – expected to become the company’s next big earner.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Woodside quits US concentrated solar project, puts green hydrogen plans on hold

In a decision Woodside says is "not particularly" related to America's new fossil fuel focus,…

22 January 2025

Fact check: No, a Queensland solar farm was not “smashed” by wild weather

A social media post featuring a fake news report is spreading a false claim about…

22 January 2025

Santos hits pause on massive Australian oil and gas project, shifts attention to US

As Trump confirms plans to "drill baby, drill" Santos hits pause on a $3bn-plus oil…

22 January 2025

Marinus Link moves closer to construction as short-list narrows down to two contenders

Marinus Link has narrowed the field for who will build the onshore infrastructure to two…

22 January 2025

Big battery joins solar farm to complete “cutting edge” hybrid renewables system

Vena Energy says it has completed Australia's largest utility-scale hybrid renewable facility with a single…

22 January 2025

Quinbrook seals record finance deal to build huge “Supernode” data centre battery

Developer Quinbrook Infrastructure starts the year with the biggest ever funding deal for a battery…

22 January 2025