The Garden Island micro-grid, located in a naval base off the port of Fremantle south of Perth, was supposed to be a shining light for the future of distributed energy, and potentially the world’s first micro-grid incorporating wave energy. But so far it hasn’t turned out that well.

Carnegie Clean Energy reveals in its latest annual report that the micro-grid – which features a 2MW solar array and and 2MW/0.5MWh of battery storage and which began operations in August, 2019 – had been plagued by “teething issues and panel failures” in its first few months that meant it wasn’t able to operate at full capacity.

And then, in early April, the plant was disconnected due to major infrastructure changes on the Naval Base. This, Carnegie says, had been expected, but out of its control. It is hopeful that it will be re-connected shortly, by which time it hopes to have resolved its technical issues.

However, the experience has been costly. Carnegie suffered an impairment of $4.7 million relating to the Garden Island microgrid in last-year’s accounts, and it is clear that revenues from the operation were below expectation this year.

The Department of Defence is spending $350 million upgrading the facilities at Garden Island and the HMAS Stirling naval base it houses, including an upgrade of the electrical system.

“Carnegie anticipates that the system should be reconnected in the current quarter, however this is subject to progress on Defence’s upgrades and is largely outside Carnegie’s control,” it says in its annual report.

“The net of costs and lost revenue associated with the reconnection process is so far consistent with expectations. Once completed, Defence’s upgraded electrical system will support morestreamlined operations of the Garden Island Microgrid.”

Garden Island is actually the main revenue earner for Carnegie, which is still chasing its dream of creating commercially viable wave energy machines, even if it had to go back to the drawing board after losing a promised grant from the W.A. government and ARENA last year.

It is now working on “wave predictor” technologies and smart controls, before seeking to rollout the latest version of its CETO technology that it still hopes can be deployed in places such as remote islands, near Garden Island, or perhaps near Albany off the south coast of W.A.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Compressed air battery wins state approval for Silver City blackout fix in Broken Hill

The long duration compressed air storage project has NSW development approval and soon will have…

25 February 2025

Italian company behind “carbon dome” energy storage sets up a base in Melbourne

Italian long-duration energy storage company sets up APAC headquarters in Melbourne as it looks for…

25 February 2025

Likely new German coalition still firmly attached to net zero by 2045, even with Greens on outer

Likely new German leader not known for fierce climate advocacy, but does recognise need to reduce…

25 February 2025

Who will take on the emissions of Australia’s most polluting coal mine if Gupta sells?

Sanjeev Gupta is looking to pass the Tahmoor coal mine to its ninth owner for…

25 February 2025

Trump-lite: Coalition promises purge of experts who call out nuclear bunkum

Federal Coalition ready to take leaf out of Trump's playbook and attack key institutions and…

25 February 2025

Energy giant cites big battery progress as it prepares to shut down one of Victoria’s last coal generators

EnergyAustralia says investment in new storage – up to 1.6 GW by 2030 – will…

25 February 2025