Flinders Island to go 60% renewable with portable storage system

Published by

Another Bass Strait island is set to begin the shift to renewables, with Hydro Tasmania confirming it would soon start developing a “hybrid energy hub” combining wind, solar and storage on Flinders Island – an off-grid community 54 kilometres off Tasmania’s north east coast.

Hydro Tasmania, which has had great success with a similar project on the nearby King Island, says the Flinders Island project – which, as of today, is backed by ARENA to the tune of $5.5 million – aims to use a range of technologies to supply the majority of its energy needs with renewables within two years.

Not unlike the above-mentioned King Island Renewable Energy Integratiuon Project, the $12.88 million Flinders Island project will combine solar, wind and battery storage to cut its costly diesel fuel habit – in this case, by upwards of 60 per cent.

This will involve the integration of wind and solar generation with the existing diesel power station, as well as the installation of enabling technology, such as flywheel and battery energy storage, in a new form designed to drive down the cost of these systems.

Conceptual diagram of Flinders Island Hybrid Energy Hub, showing extensions to existing power station. Source: Hydro Tasmania

 

But unlike KIREIP, the Flinders project will trial the use of modular units to house and ship the key technologies – an exciting, Tasmanian-made innovation that is being developed and tested for the first time through the Hybrid Energy Hub.

Hydro Tasmania hopes the modular units – developed in conjunction with local Tasmanian manufacturers – will provide a low-cost and scalable solution for rapid transport and installation of renewables; one that could also be used for such applications as disaster relief, or for powering the mining industry.

ARENA CEO Ivor Frischknecht described the development of the portable hybrid energy solution as one of the project’s most exciting aspects, with its potential to drive down costs and deliver a commercially competitive product.

“This low-cost, scalable approach has the potential to be a real game changer in remote areas – reducing the amount of construction and engineering work needed to be carried out on site would significantly reduce costs, risks and construction time,” Frischknecht said in a statement accompanying Wednesday’s funding announcement.

“Technologies like storage and dynamic resistors smooth out the power generated from solar and wind, while the automated control systems ensure generation and enabling equipment are coordinated and perform when required.

“Australia is a large country with many off-grid communities and industries facing similar energy supply challenges, whether they are on islands or in remote locations on the mainland.”

Hydro Tasmania has already seen one such opportunity in Energy Developments Limited’s Coober Pedy project, incorporating wind, solar and enablers, which aims to achieve a 70 per cent reduction in diesel fuel used for power supply to the township of Coober Pedy.

The company has been assisting EDL with the development phase of this project which would make use of the Tasmanian designed and manufactured modular enabling units if it proceeds to implementation.

“This knowledge sharing will ensure we are best placed to advance competitive, reliable renewable energy options for off-grid Australia and help reduce its reliance on trucked and shipped in diesel,” said Frischknecht.

The Flinders Island project is scheduled for completion in November 2016.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Game on: How major sporting events boost private jet travel, and transport emissions

If those traveling by private jet to major sporting events had taken commercial flights instead,…

8 July 2026

Renewables head off grid, but wind farms last longer than many mines, and that’s a problem

WA's shallow energy market leads some developers to look to miners to backstop demand, but…

8 July 2026

No more “bragawatts:” Some investors not convinced that bigger is better for wind projects

Fewer investors, more demand, and huge projects are changing how financiers grade different wind options…

8 July 2026

Struggling wind projects warned their unused capacity will be returned to future CIS tenders

Owners of wind projects struggling to get finance have been warned by the federal government…

8 July 2026

Why electricity networks need to understand people, not just poles and wires

More than a billion data points from the Electrify 2515 trial should help networks replace…

8 July 2026

CIS-winning wind farm finally starts construction, more than a decade after first unveiling

One of the first wind projects to win a CIS deal has finally begun construction,…

8 July 2026