Renewables

First stage of what will be Australia’s biggest wind project gets ready to inject power into grid

Published by

The first stage of the Golden Plains wind project in Victoria, which will be the biggest in Australia when complete, has entered the market operator’s grid management system and will soon be ready for testing and commissioning.

Golden Plains is divided into two stages, east and west, and will total 1,333 megawatts (MW) when both stages are finished in 2027, overtaking the 923 megawatt (MQW) MacIntyre wind project in Queensland.

But Golden Plains may also be first to market, with its first 756 MW stage already entering the grid management system, according to Geoff Eldridge of GPE NEMLog, which enables it to begin testing and start to work through the commissioning process, which could take another five to six months.

The $3 billion project, which will also include a big battery – possibly sized at 300 MW and several hours of storage – began construction in 2023, and obtained its connection approvals from the Australian Energy Market Operator in just five months, around half the time normally expected.

Golden Plains is the third new wind project in Victoria to enter the grid management system in recent weeks.

Just last week, the 218 MW Ryan’s Corner wind project owned by Global Power Generation near Port Fairy officially entered the AEMO Market Management System (EMMS) and the nearby 89 MW Hawkesdale wind farm entered the MMS in late May.

The Hawkesdale wind project is now on a 30 MW hold point as it works its way through the commissioning process towards full capacity.

At Golden Plains, more than one quarter of the 122 turbines in the first stage of the project have already been erected, and construction of the 93-turbine second stage began in June after a financing deal was landed with Australia and overseas banks.

Construction on the first stage of Golden Plains started in early 2023. MacIntyre started construction in 2022 and was going to be sized at more than a gigawatt, but one 103 MW component was withdrawn by the state-owned CleanCo last year because of connection delays and rising costs.

It is yet to enter AEMO’s grid management system, GPE NEMLog’s Eldridge says.

However, MacIntyre will have the opportunity to double in size with the 1,000 MW Herries wind component, part of the broader MacIntyre precinct, also now working its way through the planning process.

Golden Plains is using V162-6.2MW wind turbines from Danish turbine maker Vestas. It is majority owned by TagEnergy.

It has signed power purchase agreements with Equinox, Snowy Hydro and Ikea and hopes to also secure an underwriting agreement through the federal government’s Capacity Invesgment Scheme.

It has also partnered with retailer Energy Locals to provide eligible residents within a 3km radius of the turbines with up to $1600 per annum in credits, equivalent to the annual usage of an average Victorian home, by switching to Energy Locals.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Amazon inks its first ever standalone battery tolling agreement – with a project in East Gippsland

Global web services giant signs its first ever standalone battery "tolling" agreement, globally, in a…

2 September 2026

“Bloody dangerous territory:” World on track to exceed 1.5°C warming

Earth is on track to exceed 1.5 degrees of warming within years, the United Nations…

2 September 2026

“Fully funded, fully contracted:” Construction team ready to go on state’s largest solar-battery hybrid

Frontier Energy says it has secured all major contracts to start construction later this month…

2 September 2026

Grid Connections 2026: Who’s going where and doing what in Australia’s green energy transition

New CEOs at CS Energy, CER, Ark Energy and Western Power; new role and hire…

2 September 2026

Scrapping VNI-West will “guarantee a massive increase” in power bills, former energy minister warns

Scrapping VNI-West and other projects designed to support renewable energy will result in "massive" electricity…

2 September 2026

Fortescue green iron rival wins Arena cash to scale up Perth demonstration plant

Element Zero, the upstart Pilbara green iron contender and survivor of a legal challenge from…

2 September 2026