Final blade arrives to complete biggest wind farm in NSW

Published by

Less than a year after the Rye Park wind farm began generation from its enormous turbines, the last of 198 blades has arrived at the New South Wales site.

The 396MW project, near Yass in the NSW Southern Tablelands, and currently the biggest in the state, received the final 80m-long blade overnight – driven from the Port of Newcastle, owner Tilt Renewables said in a LinkedIn post.

The completed wind farm will host sixty six 6MW V162 Vestas turbines, each with a tip height of 200 metres. The farm is anticipated to produce on average 1,188 gigawatt hours (GWh) of electricity a year.

Tilt Renewables expects the wind farm to the fully operational by the middle of this year, completing a three-year construction effort on NSW’s largest wind farm.

When Rye Park began being built in 2021 the Vestas turbines were the largest to ever have been erected in Australia, but they were pipped last month by the Golden Plains wind farm which installed a 6.2 MW turbine.

Rye Park turbines.

About 55 per cent of energy production from the Rye Park wind farm is contracted to mining company Newcrest Mining under a 15-year power purchase agreement that will supply the Cadia gold mine in NSW.

The remainder is going to AGL Energy, which signed a 15-year power purchase agreement over the other 45 per cent and for the associated large-scale generation certificates (LGCs), which it’s on-selling to Microsoft.

LGCs are currently trading at $45 each.


Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by

Recent Posts

Tallest turbines and longest blades arrive in Australia for 300 km road trip to Pilbara wind site

The longest blades and tallest turbines seen in Australia arrive at port and are now…

26 July 2026

Peter Hannam joins Renew Economy as senior writer as editorial team expands

Veteran energy and climate reporter Peter Hannam is joining Renew Economy, returning to journalism after…

24 July 2026

Energy Insiders Podcast: Why we make renewable projects so hard

Consultant Shane Quinnell on the many hurdles we force renewable projects to jump over –…

24 July 2026

“Strong endorsement:” Australia’s biggest solar-battery hybrid project locks in finance

Ark Energy becomes the fifth developer in just one week to announce a major investment…

24 July 2026

Australian developer gets funding boost for 2 GW-plus renewable energy plans and big solar battery hub

The developer behind Victoria’s Mortlake Energy Hub has secured around $A245 million from a global…

24 July 2026

Small victory for big wind project navigating tough state planning laws

Plans to build a wind farm near one of country's youngest coal plants win all-important…

24 July 2026