Policy & Planning

Small victory for big wind project navigating tough state planning laws

Published by

Plans to build a wind farm near the coal town of Millmeran in Queensland’s Toowoomba region are still alive and kicking after the local council granted a lifespan extension for a meteorological mast at the proposed project site in Captains Mountain.

The up to 252 megawatt (MW) Captains Mountain wind farm is being proposed for development by Danish giant Vestas on land near the Millmerran coal fired generator – one of the youngest coal power plants in Australia’s remaining fleet.

The up to $700 million project joined the queue for federal environmental assessment in March of 2025, and proposes to install up to 35 wind turbines on land predominantly used for cattle grazing, animal husbandry and related rural activities.

This week’s approval of a change to the development application, small though it might be, is a positive sign for the proposed wind farm that it has council’s support, a factor that carries more weight than ever under Queensland’s current renewable energy planning and development rules.

In its most recent community newsletter, the Captains Mountain team said it continues to work closely with Toowoomba Regional Council to finalise the Social Impact Assessment (SIA) and to make a start on a Community Benefit Agreement (CBA) under the “updated requirements.”

“Our team is steadily working through the remaining steps of the assessment process, and we expect to lodge our development application once all documentation is complete,” the newsletter says.

Queensland’s updated planning framework for renewables projects was unveiled by the LNP government last year after it ripped up the state’s official renewable energy targets, cancelled the approval of two proposed wind projects, and “called in” a number of other wind and battery projects whose fate remains undecided.

The crackdown on planning approvals has been led by planning minister and deputy premier Jarrod Bleijie, and effectively provides veto rights on new projects to local councils.

Vestas says it has identified the Captains Mountain area for its strong wind resource and is using a range of innovative instrumentation and data analysis techniques to model the resource characteristics at the proposed site – including via the meteorological masts, or metmasts, that were the subject of the recent council vote.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

To support independent media, and combat AI slop, you can click here to make a one off donation or become a regular supporter of Renew Economy.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Vestas

Recent Posts

Chickens “coming home to roost” for next Victorian energy minister, whoever it might be

The coming three years will be exceptionally tough for Victoria's next energy minister, experts say.

28 October 2026

World’s biggest battery maker snags deal for new Australian project, sees “huge interest” in sodium tech

China battery giant reveals it has been selected as the tech partner for a major…

28 October 2026

Victoria Coalition promises quick review of transmission plans, as it soft pedals stance on renewables

Victoria's likely next energy minister seeks to woo clean energy summit, promising quick fire review…

28 October 2026

Andrew Forrest’s Fortescue signs first 3rd party supply deal for its giant Pilbara “green grid”

Andrew Forrest's Fortescue signs up owner of huge lithium mine as the first customer of…

28 October 2026

Wind and solar projects to be given revenue certainty in new market design to back 75 pct renewables target

Updated: A simplied version of the new national policy mechanism will be used to propel…

28 October 2026

WA wants more renewables, but that does not mean it needs more gas

W.A. should easily meet its 75 pct renewables target, but there is a big question…

28 October 2026