EnergyAustralia signs PPA for 113MW wind farm in NSW

Published by

Infigen Energy’s proposed 113MW Bodangora wind farm in New South Wales has become the latest large-scale renewable energy project to secure a power purchase agreement, this time with EnergyAustralia, marking the major retailer’s fourth PPA in just three months.

Infigen said on Tuesday that it, and the project’s development partner, had signed a PPA with EnergyAustralia for 60 per cent of the output (electricity and LGCs) from the proposed wind farm that is being developed near Wellington.

 

The deal, which is conditional to the project achieving financial close within an agreed timeframe, commits EnergyAuystralia to buy just over half of the wind farm’s output from the time it is switched on, to December 31, 2030.

The balance (40%) of Bodangora’s output will be actively managed within Infigen’s energy markets risk framework, Infigen said.

With the PPA signed, Infigen is moving to wind up development tasks for the Bodangora project, which includes closing an in-principle agreement for Infigen to acquire its development partner’s 50 per cent equity interest in Bodangora for an agreed amount, prior to financial close.

This will leave Infigen as 100 per cent owner of the Bodangora project, responsible for the equity component of construction funding, which can be funded from existing cash reserves.

“We are pleased to be able to announce this important step towards our goal of proceeding to construction of a new wind farm,” said Infigen managing director Ross Rolfe.

“We are working diligently towards finalising other elements of the project in order to reach a final investment decision and financial close.”

EnergyAustralia, meanwhile, has now secured PPAs for a total of 285MW of renewable energy, putting it well on the way to achieving its goal of 500MW.

Earlier this month, the gentailer – which also owns two of Australia’s largest coal-fired power plants – signed a PPA for all the electricity generated by what will be Victoria’s first large-scale solar project, the Gannawarra Solar Farm.

And last December, EnergyAustralia signed a PPA for the output of the 48.5 MW solar farm at Manildra in regional New South Wales until 2030.

“We’re really please to add a quality project like Bodangora to our power purchase portfolio,” said EnergyAustralia managing director Catherine Tanna in a statement on Tuesday.

“The reality is these are the projects that will underpin Australia’s future energy mix and it’s up to us to provide the support they need to get built,” she said.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“Sick joke:” Beetaloo gas starts flowing as new UN report issues “deafening” climate wake-up call

As the NT marks first gas from the huge Beetaloo "carbon bomb," the Pacific Islands…

1 September 2026

From diesel shackles to solar sovereignty: How Australia can help unlock a renewable Pacific

Behind the Pacific’s reliance on fossil fuel imports lies an extraordinary economic opportunity. But tapping…

1 September 2026

Wind giant gets green light to plug batteries into turbines at 300 MW project, deliver an Australian first

Plans to add batteries to three-quarters of the turbines at a proposed 298 MW wind…

1 September 2026

Outgunned: Five fossil fuel lobbyists spent $553,000 on Meta ads in August, the renewables industry just $3,090

Fossil fuel lobbyists are flooding social media with ads, outgunning the minimal effort of the…

1 September 2026

How three hours of free solar power can cost you more | SwitchedOn Australia

Solar Sharer exposes a fundamental problem with our energy system – protecting retailer revenues can…

1 September 2026

“Retailer viability” trumped bill savings in Solar Sharer design, says energy veteran

A policy designed to give households access to abundant free solar power has been nobbled…

1 September 2026