Commentary

Do Fortescue’s plans to eliminate gas and diesel stack up? The big win comes from electric trucks

Published by

Fortescue has taken a number of expensive “space cadet” wrong directions in its decarbonisation journey, principally around green hydrogen.

But, on a reasonable set of numbers, its Pilbara renewable plans, and in particular the electrification of diesel trucks looks like it could deliver a pre-tax internal rate of return (IRR) of close to 16 per cent.

ITK expects the Chinese suppliers will price well below normal — it’s a big market and Fortescue can serve as the showcase project.

So I’ve used two sets of capex numbers. Some very, very low numbers implied from the most recent Fortescue press release and some more, but not necessarily sufficiently, conservative numbers.

It’s the conservative numbers in the headline table. Our estimated savings are at the top end of the range mentioned by Fortescue but essentially consistent. For a desktop study it’s a reasonable result. More due diligence would no doubt result in more conservative estimates.

Figure 1: fortescue_irr_headline

It’s the electric trucks that justify the project economics. The other uses of the solar and wind to replace existing gas generation and avoid new gas generation are nice to have but would struggle to earn IRR.

But the truck electrification benefits appear to be excellent. There is also an interesting competition between in-truck batteries and battery swap. In this application I expect battery swap to be the winner.

More detail on these numbers is provided below. For me the two key risks are the wind turbines used, not really commercially tried and tested particularly in high wind conditions or as to actual cost, and the Iron Bridge magnetite scale up, already well over budget and years behind schedule.

And I could easily be underestimating the transmission capex but it’s still unlikely to change the overall economics materially. The numbers in the above table are not this year’s diesel costs. The payback is far better at current diesel costs but then the project will take until 2030 to complete.

$4 bn of wind, solar, battery and transmission capex

Fortescue is building 1.2 GW of solar and 0.6 GW of wind, about 700 km of transmission and some batteries at a total cost of at least $A4 billion.

This will replace about 13 PJ of gas consumed in Hematite processing, magnetite processing, Port, and other operations. In total that’s between 300 and 350 MW of demand on my estimates. This is a relatively low IRR project in the absence of a carbon cost and will eventually strand a gas pipeline and the Solomon power station. Or at least reduce them to standby.

It also supports a much higher IRR truck electrification program. ITK estimates that if the electric trucks cost roughly the same as diesel trucks, until recently a laughable assumption – but no longer – then given an electricity cost of maybe A$95/MWh and diesel delivered cost net of rebate at around A$157/litre the cash savings are in the order of $0.5 billion per year. Those electricity prices depend on a few optimistic assumptions.

In the process of electrification Fortescue will have the chance to improve the economics of its troubled Magnetite plant, plagued by water pipeline leaks and more worrying air separation opex issues. The Magnetite plant (Iron Bridge) uses novel dry rolling instead of wet crushing.

As with many a new process it hasn’t gone smoothly (particularly the dry ore has been highly abrasive on the air separation circuit media) and so capital costs increased from US$1.9 bn to over US$4 bn requiring a book value write-down, and output for a plant announced in 2019 remains far below capacity and is not currently scheduled to hit full capacity until 2028.

    The map below shows the scale of the Pilbara operations and the distances involved.

    Figure 2: Fortescue Pilbara operations

    Demand 530 MW all up

    Figure 3: image-20260413161023562

    All of the electricity demand already exists other than the truck charging. The accommodation for 10,000 people, port and ancillary are both full-on seat-of-the-pants estimates and incidental to the main story. The Iron Bridge demand is at full capacity. Fortescue has still not proved the novel dry process is capable of reaching full capacity.

    A summary of the generation system is:

    Figure 4: generation

    Most of the existing supply comes from the 315 MW Solomon Power Station, which consists of gas reciprocating engines supplied by the 270 km Fortescue River Gas Pipeline. The pipeline delivers around 15 PJ per year, which at $8/GJ costs say A$130 m a year. The gas cost might be less.

    In addition, from 2025 there is the fully commissioned 100 MW North Star Junction solar farm. I used the renewables-ninja system synthetic wind profiles with standard 6 MW turbines to get a wind profile. Only one year of weather data was provided, but should do for this purpose. The gas system will no doubt remain for backup.

    It can be seen that on an average day there are long periods where even with the battery, supply falls below demand. Howeve,r for an average day this is overcome by adding more swap packs into the system than are strictly needed.

    Average day supply and demand balance

    Figure 5: fortescue_daily_energy_balance

    Note this is very much the average day. Wind output varies quite a lot as can be seen in the generation system figure above. Gas will supply the missing output. At the moment the assumption is that surplus generation is spilled.

    Diesel electrification

    The overall picture is very simple. It costs a lot less to run a truck on electricity for an hour than it does on diesel.

    Figure 6: image-20260413191147833

    In chapter and verse…

    The Diesel Baseline

    Fortescue consumes approximately 700 million litres of diesel per year across its Pilbara operations, making it one of Australia’s largest diesel consumers.

    This diesel is delivered by ship from Singapore to Port Hedland, then road-tankered 145–450 km to mine sites. Every 10 cpl movement in diesel prices has a ~$70M impact on operating costs.

    Delivered diesel cost (net of Fuel Tax Credit):

    ScenarioDelivered priceNet of FTC (52.6 cpl)Annual cost (700 ML)
    Normal market$1.80–2.10/L$1.27–1.57/LA$890–1,100M
    Current crisis (Hormuz)$3.20–3.50/L$2.67–2.97/LA$1,870–2,080M

    Sources: AIP terminal gate prices; (Campbell, 2024); Fortescue sensitivity disclosure ($70M per 10 cpl).The diesel goes almost entirely into the mining fleet — haul trucks (60–70%), excavators and loaders (15–20%), drill rigs, dozers, water carts, and graders (~15–20%). Processing plants, conveyors, and accommodation are already electrically powered.

    Fleet Composition by Mine Site

    Fortescue has ordered 360 battery-electric haul trucks from two suppliers — Liebherr (T264 BEV) and XCMG (XDE240 BEV) — plus 100+ ancillary electric vehicles (Fortescue Ltd, 2024a, 2024b; International Mining, 2025).

    The allocation across sites is not publicly disclosed. The following estimates are based on relative production volumes, pit complexity, and haul distances:

    Table: Estimated fleet and charging infrastructure by mine site

    Mine siteProduction (Mtpa)Est. trucksCharging modelEst. chargers or swap baysEst. infra cost
    Solomon Hub (Firetail + Kings)~70120–150MCS + swap18–22 chargers + 1–2 swap stationsUS$100–140M
    Cloudbreak / Christmas Creek~60100–120MCS + swap15–18 chargers + 1–2 swap stationsUS$85–120M
    Eliwana~3060–80MCS (first BEV trials here)9–12 chargersUS$45–65M
    Iron Bridge~2220–40Swap (shorter hauls)1 swap stationUS$15–25M
    Rail, port, ancillary60+ ancillaryDepot chargingVariousUS$30–50M
    Total~190~360 trucks + 100+ ancillaryUS$275–400M

    Note: Truck allocations are ITK estimates based on production volumes and material movement. Charging infrastructure costs from McKinsey (US$700k–1M per truck) and ICMM/Mining3 benchmarks.

    Truck Economics

    The following are just internet search estimates. As with the rest of this note no humans were interviewed. Traditional due diligence it definitely is not. The capital costs are sheer guesses and might reflect actual or introductory prices and/or be wrong.

    Table: 240-tonne class haul truck comparison

    SpecificationCat 793F (diesel)Liebherr T264 BEVXCMG XDE240 BEV
    Payload (tonnes)227240230
    Engine/motor power (kW)1,9763,200 (peak)1,865
    Battery capacity (MWh)3.2Not disclosed (BYD Blade LFP)
    Fuel/energy consumption137–182 L/hr diesel~86% lower cost/tonneNot disclosed
    Charging methodRefuel ~15 min6 MW MCS (~30 min)Battery swap (~15 min)
    Purchase price (est.)~US$5–6M~US$6–8M~US$3–4.5M

    Sources: Cat 793F OEM specifications; Liebherr T264 product data; LECTURA specs (XCMG XDE240); (Fortescue Ltd, 2024a) (implied pricing).

    Per-truck annual economics

    ItemDiesel (Cat 793F)Electric (BEV)
    Fuel/energy cost~A$1.5M/yr~A$0.25M/yr
    Maintenance~A$0.48M/yr~A$0.34M/yr
    Total operating~A$2.0M/yr~A$0.59M/yr
    Annual saving~A$1.4M/truck

    Assumptions: 6,000 operating hrs/yr, diesel 160 L/hr at $1.57/L net of FTC, electricity at A$91/MWh (Phase 1 LCOE), 500 kWh/hr electric consumption, 30% maintenance saving on BEV.

    BEV premium: ~A$2–3M per truck (Liebherr ~A$3M, XCMG ~A$1–2M over diesel equivalent).

    Simple payback: 1.5–2 years per truck at normal diesel prices. Under 1 year at crisis prices.

    Fleet-wide economics

    MetricValue
    Fleet size360 trucks
    Annual diesel saving (fleet)~A$450M/yr
    Annual maintenance saving (fleet)~A$50M/yr
    Total annual saving~A$500M/yr
    BEV premium (fleet)~A$900M
    Charging infrastructure~A$400–600M
    Total incremental investment~A$1.3–1.5B
    Fleet payback2.6–3.0 years

    In general I believe in-truck batteries will out compete battery swapping. However for this particular integrated operation battery swapping provides an ideal way to take advantage of a flat load with solar-heavy generation.

    I won’t personally be surprised therefore if over time fewer Liebherr and more XCMG trucks end up in the fleet. This is sheer speculation.

    Charging Infrastructure

    Two models in the fleet

    Fortescue will operate two charging approaches, matching the two truck suppliers:

    Liebherr T264 BEV — MCS fast charging:

    • 6 MW Megawatt Charging System with robotic connection (ABB/Liebherr)
    • ~30 minute charge for 3.2 MWh battery
    • Chargers located at pit-edge and dump-side
    • US$3–5M per charger installed (US$2–3.5M at scale)
    • 1 charger per 6–8 trucks (with redundancy)

    XCMG XDE240 BEV — battery swap:

    • Robotic swap station: depleted pack out, charged pack in
    • ~15 minute swap time (vs 30 min MCS charge)
    • Standardised 400 kWh BYD Blade LFP packs — same pack across trucks, excavators, and loaders
    • US$5–10M per swap station + US$250–400k per spare pack
    • Float ratio: 1.3–1.5 packs per truck

    Why not trolley assist?

    Trolley assist — a tram line powering trucks up the pit ramp via overhead catenary or Liebherr Power Rail — was considered. In this case I don’t think it makes sense, and there is no mention of it in the releases.

    Swap Packs as Distributed Energy Storage

    The spare packs at swap stations represent additional storage that helps the renewable system manage the solar/wind intermittency problem.

    Fortescue’s Phase 1 renewable system (1.2 GW solar + 600 MW wind) produces ~4,836 GWh/yr against ~530 MW average demand. But generation and demand don’t match hour by hour:

    • Midday: solar produces ~1,000 MW. Demand is ~530 MW. Surplus of ~470 MW — needs to be stored or curtailed.
    • Overnight: solar is zero. Wind averages ~216 MW. Demand is still ~530 MW. Deficit of ~314 MW — needs to come from storage.
    • Multi-day low wind: if wind drops below 20% CF for 48 hours, the 4.5 GWh grid battery depletes in ~10 hours at 450 MW discharge.

    The grid battery (4.5 GWh at 4-hour duration) can shift ~4–5 hours of daytime surplus to the evening, but it cannot cover a full 12-hour overnight gap, let alone a multi-day low-wind event.

    Swap packs can add ~0.36 GWh of storage

    Each spare battery pack at a swap station is ~3 MWh. We model about 120 surplus packs above normal requirements to help keep the trucks operating say 6,000 hours a year.

    But the real flexibility comes from scheduling when the packs charge:

    • Low-wind events: maintain a buffer of fully charged packs (say 50 packs = 150 MWh) that can extend truck operations for 4–6 hours beyond normal, buying time for wind to recover.

    The swap model turns 120 spare packs into a flexible 120 MW / 360 MWh demand response resource.

    If Fortescue wanted to extend the swap buffer specifically for grid resilience, additional packs are cheap:

    • 50 extra packs × 3 MWh × A$250/kWh = A$37.5M for 150 MWh of additional storage
    • 100 extra packs = A$75M for 300 MWh

    Total Diesel Replacement Investment

    Table: Fortescue diesel replacement — total cost summary

    ComponentCost (A$)Notes
    360 BEV trucks (premium over diesel)~900MLiebherr ~A$3M premium, XCMG ~A$1.5M premium
    100+ ancillary BEV equipment~570MXCMG US$400M contract (loaders, dozers, water carts)
    50+ electric drill rigs~500MEpiroc US$350M contract
    MCS chargers (~45 units)~250MUS$3.5M avg installed
    Swap stations (~5 units)~75MUS$10M avg + spare packs
    Grid connection and distribution~100MSubstations, HV cable at each site
    Total diesel replacement~A$2.4BAll USD converted at AUD/USD 0.70

    Annual savings:

    ItemA$/yr
    Diesel fuel avoided (700 ML at $1.57/L net)~1,100M
    Maintenance reduction (~30% on BEV fleet)~50M
    Less: electricity cost (at A$91/MWh LCOE)(350M)
    Net annual saving~800M

    Simple payback on diesel replacement: ~3.0 years.

    The payback calculation also excludes the $90 m of additional capex for surplus swap packs. Those packs barely move the payback needle.

    Timeline to zero diesel

    DateMilestone
    Sep 2024US$2.8B Liebherr partnership announced (360 T264 BEV trucks)
    Nov 2024US$400M XCMG ancillary equipment contract
    Apr 2025US$350M Epiroc electric drill rig contract
    Sep 2025XCMG added as second haul truck supplier (150–200 units)
    Early 20264 autonomous BEV trucks in validation at Eliwana
    2026First BEV production trucks operational in Pilbara
    2026–2028Progressive fleet replacement across all sites
    2028–2030XCMG BEV deliveries (phased)
    2030Real Zero target — no diesel in Pilbara operations

    Detailed summary of costs and benefits

    Figure 7: fortescue_electrification_irr

    The table above brings together the full capex and benefit picture. The optimistic capex numbers are those implied in phase 2 of FMG’s asx release

    On the conservative set of numbers the combined renewables-plus-diesel-replacement program delivers a pretax IRR around 16%, driven overwhelmingly by truck electrification savings. The key risks remain wind turbine performance, Iron Bridge ramp-up, transmission cost and whether XCMG pricing holds at scale.

    Note: Savings Reconciliation

    Three different annual saving figures appear in this analysis. They measure different scopes:

    MetricA$/yrScope
    Truck fleet operating saving550M360 trucks only. Fuel + maintenance saving. Gross of electricity cost
    Diesel replacement net saving800MAll diesel (700 ML — trucks + excavators + drills + ancillary). Net of electricity at A$91/MWh LCOE. Excludes gas
    Full project net benefit1,208MAll diesel + all gas displaced. Net of all new opex (renewable O&M, charger O&M). Used in IRR model

    Bridging from A$550M to A$1,208M:

    StepA$M/yr
    Truck fleet saving (fuel + maintenance)550
    Add: non-truck diesel (excavators, drills, ancillary)550
    All diesel gross saving1,100
    Add: maintenance saving on all equipment50
    Less: electricity cost (A$91/MWh × ~3,800 GWh)(350)
    Diesel replacement net saving800
    Add: gas fuel displaced (existing 16M GJ + new 5.6M GJ at A$8/GJ)173
    Add: gas O&M avoided20
    Less: additional renewable/charger O&M beyond electricity(incl above)
    Adjustment: opex split difference215
    Full project net benefit1,208

    Note: the A$550M truck-only figure uses per-truck economics (160 L/hr, 6,000 hrs, A$1.57/L net diesel). The A$1,100M all-diesel figure uses the fleet total (700 ML × A$1.57/L). Diesel splits roughly 50:50 between trucks and non trucks.

    Campbell, R. (2024). Australia’s fuel tax credit and fossil fuel subsidies. The Australia Institute. https://australiainstitute.org.au/wp-content/uploads/2024/05/P1481-Australias-Fuel-Tax-Credit-and-fossil-fuel-subsidies-Web.pdf

    Fortescue Ltd. (2024a, September). Fortescue signs US$2.8 billion green equipment partnership with Liebherr. https://www.fortescue.com/en/articles/fortescue-signs-us-28-billion-green-equipment-partnership-with-liebherr

    Fortescue Ltd. (2024b, November). Fortescue awards US$400 million contract to XCMG. https://www.fortescue.com/en/articles/fortescue-awards-us\$400-million-contract-to-xcmg-to-supply-zero-emissions-mining-equipment

    International Mining. (2025, September). Fortescue signs decarb-focused agreements as it rejigs battery-electric truck build plans. https://im-mining.com/2025/09/26/fortescue-signs-decarb-focused-agreements-as-it-rejigs-battery-electric-truck-build-plans/

    David Leitch is a regular contributor to Renew Economy and co-host of the weekly Energy Insiders Podcast. He is principal at ITK, specialising in analysis of electricity, gas and decarbonisation drawn from 33 years experience in stockbroking research & analysis for UBS, JPMorgan and predecessor firms.

    David Leitch

    David Leitch is a regular contributor to Renew Economy and co-host of the weekly Energy Insiders Podcast. He is principal at ITK, specialising in analysis of electricity, gas and decarbonisation drawn from 33 years experience in stockbroking research & analysis for UBS, JPMorgan and predecessor firms.

    Share
    Published by
    Tags: Featured

    Recent Posts

    Fortescue starts construction of Australia’s biggest solar farm outside main grid, and giant eight-hour battery

    Fortescue starts building biggest solar farm outside main grid, and a giant eight-hour battery as…

    25 May 2026

    Australia’s biggest wind project and 8 battery hybrids among 19 winners of largest ever renewable auction

    Latest CIS tender dominated by wind projects and battery hybrids, with 7.8 GW of new…

    23 May 2026

    Better internet, fewer feral pigs: Renewable developers join forces with locals to make lasting change

    Work is underway on a major telecommunications upgrade – and other practical initiatives – to boost…

    22 May 2026

    CSIRO is cutting vital climate science jobs. Here’s what’s at stake for Australia

    Proposed cuts to staff in CSIRO's environment unit are likely to take in the team…

    22 May 2026

    “Not just a call centre:” Home battery contender doubles down on Australia-made strengths

    In the mad rush to home battery storage, this Australian company is doubling down its…

    22 May 2026

    Sungrow says advanced inverter trials show they can provide heart-beat of the grid in absence of coal

    Chinese power company echoes findings of Tesla and Fluence, saying tests show grid forming inverters…

    22 May 2026