Solar

Dispute between big solar farm owners, contractors and suppliers in arbitration

Published by

The dispute between the owners, contractors and suppliers of one of the biggest solar farms in NSW, the 200MW Sunraysia project, has gone to arbitration after the much delayed solar farm finally gained registration and began its commissioning process.

The various parties have been at loggerheads over who should shoulder the blame, and the costs and lost revenue, from the delays to the Sunraysia solar project, which is running at least a year late.

It finally gained its R1 registration from the Australian Energy Market Operator late last year, and is currently in the commissioning process, with lead contractor Decmil indicating on Wednesday that it may take until September to complete.

As reported previously in RenewEconomy, Decmil has been embroiled in claim and counter claim with the project owners (John Laing 90 per cent, Maoneng 10 per cent), and with the inverter supplier Schneider Electric.

The dispute has caused Decmil to follow other major contractors by withdrawing from full EPC contracting in the wind and solar industry, although it remains keen for balance of plant contracts with no connection risks, and recently landed a contract with the Ryan’s Corner wind project in Victoria.

Decmil has faced a claim of $28 million in “liquidated damages” from the owners of Sunraysia as a result of the delays, but has a counter-claim for $19 million for its milestone payments once the R2 testing is concluded.

In its half yearly presentation made to the market on Wednesday, Decmil said the dispute concerns claims for extensions of time, variations, payment of liquidated damages, return and reinstatement of security and claims concerning alleged defects.

“Decmil claims the deduction of liquidated damages, recourse to security and set-off is wrongful,” it said.

In relation to Schneider, it said that its claim (previously quantified at $28 million) would be triggered if it is determined that the invertors supplied are defective (and therefore a concurrent delay).

Despite all this, Decmil sees strong growth in large scale renewable, and opportunities created by the exit of Downer, Biosar, RCR) “because they have been unable to get comfortable with the increased risk profile associated with such projects.”

RCR collapsed under the weight and cost of multiple delayed solar projects, Biosar quit Australia and Downer also made a dramatic withdrawal from the industry.

“Decmil will only accept balance of plant projects in renewables sector and is very careful to avoid any interconnection risks,” it noted in the latest presentation.

John Laing has previously revealed £43 million ($A79 million) in losses from the Sunraysia and Finley solar farms in NSW – Finley has also been hit by grid congestion issues that could curtail its output at certain times – and has withdrawn the assets from sale until the problems are resolved.

John Laing has stopped all new investment in renewables in Australia and has put its assets up for sale, although the process for the two solar projects is on hold pending clarity over the output.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Energy Insiders Podcast: Getting the best out of the grid

Energy expert Gabrielle Kuiper on getting the best out of distributed energy resources in the…

29 November 2024

Australian homes could slash energy bills by two thirds by cutting out gas and petrol, AEMC says

Australian households could lower their bills by over two thirds if they fully electrify their…

29 November 2024

In the end, the only blackouts were in the media headlines: But there has to be a better way to do this

Blackout featured prominently in media headlines this week, but not on the grid. But as…

29 November 2024

Trina submits approval for Victoria big battery, as locals campaign against solar and storage projects

Trinasolar and Mint Renewables have now both lodged planning applications for neighbouring big batteries in…

29 November 2024

Australia to reshape manufacturing base as Greens deal excludes fossil fuels from flagship industry policy

Greens make last minute commitment to vote for $22 billion Future Made in Australia policy…

29 November 2024

Andrew Forrest seeks green tick for another wind and battery project as Clarke Creek powers up

Andrew Forrest's Squadron Energy seeks green tick for new wind and battery project in NSW…

29 November 2024