Solar

Decmil threatens further action over Sunraysia solar farm dispute

Published by

Leading engineering group Decmil has threatened further action in an ongoing dispute over payments at the heavily delayed Sunraysia solar farm in New South Wales, one of dozens of large scale wind and solar projects to have their connection and commissioning pushed back by months, or in some cases years.

Decmil revealed in December that it was booking a $14 million hit to its cash flow as a result of a dispute over payments at the 200MW Sunraysia solar farm. The failure to obtain an R1 registration with the Australian Energy Market Operator, meant the solar plant, the biggest in NSW, could not proceed to formal commissioning and begin sending output to the grid.

Sunraysia – owned by John Laing and Maoneng, and located near Balranald in the south-west of the state – is one of a number of wind and solar farms that have been fully installed, but are unable to connect because of various issues – some relating to bottlenecks and restrictions on the grid, some to new connection rules, and some for other matters.

Decmil said in December that Sunraysia Solar has refused to award an extension of time and an associated adjustment to the contracted date for substantial completion. That meant it faces delays in progress payments, including the completion milestone payment, until the issue is resolved.

Last week it said the dispute is ongoing and an AEMO report on marginal loss factors released earlier this month noted that Sunraysia is still not registered.

“Decmil is continuing to pursue its rights under the disputed solar farm contract with Sunraysia,” the company said in a statement to the stock exchange. “Decmil has received robust legal advice in support of its position. If current negotiations to resolve the dispute are not successful, the dispute will move into arbitration.”

Contractual disputes similar to this have emerged all across the market, and the risk of connection and commissioning delays and the threat of “liquidated damages” imposed by developers to cover lost revenue has seen some major contractors quit the large-scale solar market in Australia.

Downer Group announced it would do no more solar farm contracting last month, declaring it is “too hard”, and Decmil is one of a number of companies thought to have also quite the full EPC contracting market, although it is still interested in “balance of plant” contracts.

Another major listed contractor, RCR Tomlinson, collapsed in late 2018 under the weight of cost over-runs and project delays in the solar sector, and Windlab has been engaged in a drawn out dispute with its EPC contractors over who should carry the cost of the delays to the Kennedy wind, solar, battery project that has now run for more than a year.

John Laing has announced it will put its Australia wind and solar portfolio on the market, declaring that the sector in Australia had become too difficult. It made a $100 million plus write down on several of its projects in the first half, largely as a result of the uncertainty and downgrades of marginal loss factors, a method of calculating transmission losses that is no longer considered fit for purpose by many in the industry.

The Sunraysia solar farm is not the only problem facing Decmil, whose shares have been suspended for several weeks following news that it had lost a contract for a prisons facility in New Zealand, and was seeking to recover between $50 and $60 million. That dispute led to the suspension of its shares and a delay in its interim accounts.

Comment has been sought from Maoneng and John Laing.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and is also the founder of One Step Off The Grid and founder/editor of the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former business and deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Affordable nuclear? Dutton’s plan would add nearly $1,000 a year to the power bill of a family of four

A major new report finds the Coalition's nuclear plan would add $665 to the average…

20 September 2024

Peter Dutton is about to talk nuclear at CEDA. Will he be fact checked by Chris Uhlmann?

Peter Dutton is due to explain his nuclear power policy at a CEDA event next…

19 September 2024

Australia desperately needs a strong federal environmental protection agency. Its chances aren’t looking good

We know what needs to be done. But our government is showing worrying signs of…

19 September 2024

Coca-Cola to hit 100 pct renewables in Australia one year early with new contract for NSW solar

The world’s most iconic soft-drink brand will meet its goal of using 100% renewables across…

19 September 2024

“Too afraid of China:” Meyer Burger chief quits and lambasts EU for failing to defend solar industry

Departing chief of Swiss solar manufacturer reaffirms his belief that Europe can compete against China…

19 September 2024

China solar giant Trina seeks approval for biggest battery project in Australia

Chinese solar giant Trina seeks planning approval for what would be the biggest battery project…

19 September 2024