Decmil awarded $21m wind farm balance of plant works

Published by

Press Release 

Decmil Group Limited is pleased to announce that it has been awarded an engineering, procurement and construction contract worth up to $23 million, to deliver the civil balance of plant works for the Crookwell 3 Wind Farm Project.
 
The contract has a base value of $21 million, with exercisable options worth a further $2 million.
 
Under the contract, Decmil will be responsible for 16 kilometres of road construction, encompassing both new site access roads and improvements to existing site access roads. Additionally, the Company will undertake 116,000 cubic metres of bulk earthworks for hardstands, laydowns, and building pads, as well as 6,600 cubic metres of concrete in tower bases.
 
Geotechnical investigations have already commenced, with site work anticipated to commence next month. Completion of the civil balance of plant works is targeted for mid 2022. Decmil will then return to site to complete grouting after the turbine installation, whilst dependent on installation dates, this is scheduled for completion in late 2022.
 
The contract is part of a broader joint venture arrangement with RJE Global, who are undertaking the electrical balance of plant works for Crookwell 3.
The Crookwell 3 Project is being developed by Global Power Generation (GPG) and will include construction of 16 turbines, providing an additional 50 megawatts (MW) of power to the New South Wales (NSW) energy market via a 330-kilovolt transmission line.
 
The Crookwell 3 Project follows GPG selecting Decmil to deliver the balance of plant works on GPG’s 218MW Ryan Corner Wind Farm in Victoria (see ASX announcement dated 18 November 2020).
That award followed the successful electrification of the Warradarge and Yandin Wind Farms earlier in the 2021 fiscal year, for which Decmil also completed the balance of plant works.
 
Decmil CEO Dickie Dique said “the contract win was a testament to the Company’s proven track record of successfully delivering wind farm projects”.
 
“This is another contract which illustrates our ability to capitalise on the buoyant energy sector by securing work with an existing blue-chip client,” Mr Dique said.
 
“We look forward to working closely with RJE and further strengthening our relationship with them, following the continued successful progression of our joint venture at the Ryan Corner Wind Farm. “Decmil is methodically converting its tender pipeline into contract wins, as the Company transitions from a year of consolidation in FY21 to a year of growth in FY22.”
 
This ASX release was authorised by the Decmil Group Limited Board.
Share
Published by

Recent Posts

One of Australia’s biggest wind farms forced to revisit off-take deals after lengthy construction delays and repairs

The lengthy delays at what would have been the country's biggest wind farm have forced…

3 October 2026

Still in the dark: Snowy Hydro’s awkward anniversary marked without promised review of Snowy 2 costings

The public remains largely in the dark about the full cost of the giant Snowy…

3 October 2026

Energy Insiders: Australia’s diesel dependence is not normal

Amandine Denis-Ryan from IEEFA on what can be done about Australia's unique and unhealthy dependence…

2 October 2026

September was Australia’s second hottest on record, and second driest in the east, BoM data shows

For maximum readings, September came in as Australia's third warmest. For minimums, last month narrowly…

2 October 2026

Chart of the day: Ten years of diesel rebates almost pays for a new truck

Diesel fuel tax credits earned over 10 years nearly equate the price of a huge…

2 October 2026

Biggest wind farm in two years reaches financial close, the ninth in last 12 months, and a new big battery

Updated: The biggest wind farm to reach financial close in Australia in the last two…

2 October 2026