Darwin’s first big battery is now complete, but it won’t be operating until 2024

Published by

Installation of all the battery modules for the 35MW one hour Darwin-Katherine Battery Energy Storage System – the first grid scale standalone battery in the Northern Territory – has been completed, although it will not be in full operation until 2024.

The Northern Territory’s Labor government announced on Sunday that installation of all 192 Hitachi Energy batteries in the $45 million project had been completed, allowing progression to the first stages of pre-commissioning.

Construction of the Darwin battery got underway in August last year and it is being built to support increased solar power and to displace a significant amount of gas-fired generation at the Channel Island Power Station.

Although the overall spend on the big battery grew to $45 million, the expected annual cost savings have also increased to around $9.8 million per year, keeping the promise of a five-year payback period intact.

“It means we can reduce the gas turbines spinning and reduce the amount of fossil fuels being burnt,” said the territory’s renewables and energy minister Selena Uibo.

Territory Generation, which will own the battery, said the battery will support the system in the case of sudden cloud cover affecting solar output, giving time for a gas fired generators to start up if needed, rather than “spinning” and burning fuel while it is doing so.

The government says network connected commissioning of the Darwin-Katherine big battery is scheduled to commence later this year and the facility will be fully commissioned in the 2023/24 fiscal year.

“Renewable energy makes economic and environmental sense,” said Natasha Fyles, the Northern Territory’s chief minister.

“The Territory Labor Government is investing in DK BESS as an important step towards achieving 50% renewable power by 2030 and net zero emissions by 2050.

However, there are still problems with the territory’s solar farms, with four big solar farms built and sitting idle for much of the past three years because they are unable to conform to strict new standards imposed by the local market regulator.

See also RenewEconomy’s Big Battery Storage Map of Australia

 

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Should we send data centres into orbit: SpaceX, AI and the Emperor’s new clothes

Can or should data centres be sent into orbit? It might do away with land,…

20 July 2026

Network wars: Ausgrid demands lower transmissions fees as data centres gatecrash the grid

Australia's biggest DNSP is not happy that Transgrid is maxing out its network capacity, and…

20 July 2026

“Important milestone:” Finance landed for AC-coupled big battery to turn operating solar farm into hybrid

Danish renewables developer will add a two-hour big battery to an existing solar farm after…

20 July 2026

Final turbine installed at Australia’s biggest wind farm

Final turbine installed at Australia's biggest wind farm, one of the very few projects that…

20 July 2026

It needs to be more than big batteries: The triumphs and failures of Australia’s green energy transition

AEMO reports record number of newly commissioned projects in last fiscal year, but wind and…

20 July 2026

New data centre demand over next four years will be just a fraction of new home battery capacity

The increase in data centre demand is being overshadowed by the much larger increase in…

19 July 2026