Solar

Contractor settles with inverter company over solar farm, still in dispute with owners

Published by

Contracting company Decmil says it has settled its dispute with inverter supplier Schneider over the 200MW Sunraysia solar farm in NSW, but is yet to resolve its differences with the project owners.

The dispute over Sunraysia is one of the most high profile in the industry, if only because as a listed company Decmil has to release the details of the dispute to investors, as did majority Sunraysia owner John Laing before it was taken private.

There are many other disputes between wind and solar farm developers and their contractors, mostly over delays and connection issues.

But these are largely played out behind closed doors, particularly after the spectacular collapse of RCR Tomlinson and the withdrawal from the EPC market of other listed contractors, including Downer, Tempo and Decmil.

In a recent release to the Australian Stock Exchange, Decmil says it has now reached an agreement with Schneider Electric Australia to conclude their dispute in relation to the supply contract at the Sunraysia solar project.

The dispute had been triggered around the same time as the owners made a claim of liquidated damages against the contractor over project delays.

Decmil says the terms of the settlement are confidential, although it insists there will be “no material impact on its financial accounts.” It had previously warned of potential “substantial losses” from the claim that it said amounted to $19 million in the case of Schneider.

Decmil says that the resolution of the dispute with Schneider “is an enabler” for the company to progress its arbitration dispute with the Sunraysia project owners. It gave no further details on the status of those proceedings, which it has said previously amounts to around $29 million.

In additional good news, Decmil also reports it has been advised of a “conditional preferred status” as balance of plant contractor for the construction of the proposed 108MW Waddi wind project in Western Australia, owned by Tilt Renewables.

The project is close to the the 214MW Yandin and 180MW Warradarge wind farms it helped complete in 2020. An early works scope of works will be agreed to support the development phase of the project which is targeted to commence construction in late 2023.

 

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

It needs to be more than big batteries: The triumphs and failures of Australia’s green energy transition

AEMO reports record number of newly commissioned projects in last fiscal year, but wind and…

20 July 2026

New data centre demand over next four years will be just a fraction of new home battery capacity

The increase in data centre demand is being overshadowed by the much larger increase in…

19 July 2026

Solar Insiders Podcast: Why new rules for networks signal a new dawn for consumers

AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…

17 July 2026

Developer lands “complete funding package” to begin building state’s largest solar-battery hybrid

Developer says it is good to go on early works and construction of the largest…

17 July 2026

“A really big game-changer:” AEMO looks to battery inverters as syncons prove expensive and hard to find

AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…

17 July 2026

Twiggy Forrest’s Squadron abandons plan for troubled New England wind farm

Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…

17 July 2026