Longest running solar farm contract dispute finally settled after more than two years

Published by

The longest running (publicly revealed) contract dispute over the construction of a large scale solar farm in Australia has finally been settled after more than two years of stand-offs, counterclaims and arbitration.

The dispute over the 200MW Sunraysia solar farm in NSW – between lead contractor Decmil and owners John Laing and Maoneng – first came to light in early 2020 and centred over the registration and commissioning delays that plagued dozens of large scale wind and solar projects at the time.

The Sunraysia dispute came to prominence because as listed company, Decmil had to update its shareholders, and like many others at the time, it was about who was to bear the burden of any cost over-runs and lost revenues because of commissioning delays.

The nature of these disputes, deepened by frustrations over the connection and commissioning issues, led to many contractors either collapsing (in the case of RCR Tomlinson) or leaving the industry.

The Sunraysia dispute concerned claims for extensions of time, variations, payment of liquidated damages, return and reinstatement of security and claims concerning alleged defects, according to a Decmil presentation.

Decmil claimed the deduction of liquidated damages, recourse to security and set-off was wrongful. It wrote off $9.7 million in early 2020, and later revealed it was facing a claim of up to $28.7 million in liquidated damages from the solar farm owners.

“Decmil is pleased to announce that it has finalised its dispute with Sunraysia Solar Project trust in relation to the Head Contract of the Sunraysia Solar Farm project in New South Wales,” it said in a statement this week.

“The terms of the settlement are confidential, but Decmil can confirm that the settlement amount to be received is in line with its accounts.”

Another dispute, between Decmil and inverter supplier Schneider, was finalised last October, and it means the matter is now behind them.

The experience caused Decmil to limit its focus to “balance of plant” contracts for large scale renewable contracts, rather than full EPC or head contracts. It was just one of a number of big contractors to exit that part of the market.

“This settlement puts to bed a challenging chapter for Decmil and reaffirms the ability of our strengthened executive team to successfully and methodically deal with our legacy issues,” Decmil CEO Rod Heale said in the company’s statement.

He also noted that the Sunraysia solar farm is currently performing at, or above, its performance obligations “demonstrating the high-quality nature of our work.”

For Maoneng, it also brings an end to a series of problems around its operating assets. The small Mugga Lane solar farm in the ACT was put in administration last year because of a dispute around debt arrangements, and has since been sold to CleanPeak Energy.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

From niche technology to 500,000 households “taking control:” Cheaper Home Batteries hits half-million milestone

The number of Cheaper Home Batteries installations has passed the half-million mark, a huge new…

13 August 2026

Researchers “froth” over new solar recycling method that recovers 99 pct of silver from used panels

A new take on a widely used mining technique called froth flotation can recover "virtually…

13 August 2026

Power plays: Tomago’s big green switch, the Big 3’s lack of ambition, and why Snowy must change its stripes

From the country's biggest energy utilities announcing their profits and outlook, to the country's biggest…

13 August 2026

Edify Energy reaches financial close on another pair of solar and battery hybrid projects

Edify Energy reaches financial close on another pair of solar and battery hybrid projects, in…

13 August 2026

What five Fijian sparkies taught me about remote, off-grid solar and battery systems

When it comes to remote solar and battery storage solutions, the knowledge you leave behind…

13 August 2026

Tomago won’t be 100 pct renewable until 2033, but Squadron and others want to see multiple supply deals

It will take at least six years to make Australia's largest aluminium smelter 100 per…

13 August 2026