Solar

Contractor confirms $9.7m write-off on Sunraysia solar farm, pursues inverter supplier

Published by

Decmil, the lead contractor for one of the country’s biggest solar farms, the 200MW Sunraysia facility in south-west NSW, has confirmed it has taken a $9.7 million write down on the value of its contract, and in turn has initiated proceedings against inverter supplier Schneider.

The dispute involving Decmil, the Sunraysia solar farm owners John Laing and Maoneng, and the inverter supplier Schneider arose from the delays and registration for the solar farm, which is still working through its commissioning process.

Such delays – and disputes – have been a regular feature of the Australian market given the sheer scale of new wind and solar projects, and the many changes to connection rules and the complexity of modelling.

However, few disputes come into the public domain, and the one around Sunraysia only does so because two of the parties – Decmil and the UK-based John Laing – are listed entities and need to make full disclosure to investors.

In its latest annual result posted on Thursday, Decmil says the dispute in relation to the “head contract” is ongoing, and confirmed that a “moratorium” or stay of proceedings had been put in place pending the full commissioning of the solar farm, now expected in October after the final “hold point 3” testing is complete.

It says the dispute concerns claims for extensions of time, variations, payment of liquidated damages, return and reinstatement of security and claims concerning alleged defects. Decmil claims the deduction of liquidated damages, recourse to security and set-off is wrongful.

“Separately, Decmil is advancing claims against Schneider Electric in an arbitration, which has commenced, in respect of Schneiders performance of the Supply Agreement.”

It says: “In so far as it is determined that the inverter supplied are defected (and therefor a concurrent delay) then Decmil will claim the loss suffered … under the supply contract.”

Following the Sunraysia problems, Decmil has followed other EPC contractors out of the market and focused only on lower risk “balance of plant” contracts.

It recently completed $151 million of projects on the Yandin and Warradarge wind farms in Western Australia, a $21 million contract for the Crookwell wind farm in NSW, and a $51 million for the balance of plant works at the Ryan Corner wind farm in Victoria.

Decmil says that without the Sunraysia write down its net result for the year (it also builds roads and other infrastructure) would have been a $1.8 million loss, but the write down sent it to a bottom line loss of $11.5 million.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Origin wants to supersize the Eraring battery to make it easily the biggest in the country

Origin Energy seeks approval for new addition to its Eraring battery that would take the…

5 October 2026

Going full hybrid: Massive, $2 billion solar and battery proposed at site of newly expanded wind farm

More projects are going hybrid: A $2 billion solar and battery addition is proposed to…

5 October 2026

Where’s Evo? The missing network in Canberra’s bold electrification experiment

Canberra is becoming a real-world laboratory for mass electrification, but its local electricity network will…

5 October 2026

Not a “dealbreaker:” Big Victorian wind project doesn’t need VNI West

The Macorna wind project will have a simpler ride through state planning, and insists it…

4 October 2026

Huge 195-tonne transformer arrives at big battery site after 1,300 km road trip

One of the heaviest and longest road trips ever undertaken in Australia's energy transition has…

4 October 2026

Australia is making big bets on a slow transition, but the technology S-curve tells a different story

Australia has a choice between investing in the future we can already see – or subsidising…

4 October 2026