Concrete milestone at Forrest wind farm, with more than half of turbine foundations complete

Published by

Andrew Forrest’s renewables outfit Squadron Energy has poured 35 of the 69 turbine foundations for its Uungula wind farm, taking it past the halfway mark on the New South Wales project. 

The 414 megawatt (MW) Uungula wind farm near Wellington in NSW will be the largest in the state, once complete – until others such as the massive, recently approved 1.45 gigawatt (GW) Yanco Delta project is built.

The latest milestone for the project was announced on the weekend by Tattarang – the private investment group of Andrew and Nicola Forrest – in a LinkedIn post.

It follows last month’s news that a team from Leading Edge Helicopters had started work attaching 11km of 330 kV single circuit transmission line to 28 transmission towers that will connec the wind farm to the grid in central western NSW.

Squadron’s general manager of contracts and controls, Mark Hunt, said at the time that construction of the wind farm was well underway, with turbine components, including blades, set to make the journey from the Port of Newcastle in coming months.

“I want to thank the local community, our contractors and our partners for their support to reach this stage of the project, which is creating 262 jobs and investing $41 million in the regional economy,” Hunt said in February.

“We are continuing to work hard to make sure that the project is creating a positive legacy in the region by investing in long term projects that matter to the community – including partnering with Dubbo Regional Council to deliver a new advanced wastewater treatment facility in Dubbo.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Edify Energy reaches financial close on another pair of solar and battery hybrid projects

Edify Energy reaches financial close on another pair of solar and battery hybrid projects, in…

13 August 2026

What five Fijian sparkies taught me about remote, off-grid solar and battery systems

When it comes to remote solar and battery storage solutions, the knowledge you leave behind…

13 August 2026

Tomago won’t be 100 pct renewable until 2033, but Squadron and others want to see multiple supply deals

It will take at least six years to make Australia's largest aluminium smelter 100 per…

13 August 2026

Squadron Energy lands $2.7 billion refinance deal to add flexibility

"Twiggy" Forrest's renewables outfit has refinanced its portfolio in a deal backed by 15 banks,…

13 August 2026

Big, four-hour battery that survived long-distance objectors hits financial close, moves to construction

A big battery project that survived a challenge from long-distance objectors has now reached financial…

13 August 2026

“We start our gas fleet less:” Batteries cut costs and emissions, and Origin says renewables still cheapest option

Australia's largest energy retailer confirms renewables are cheapest source of new generation, says batteries can "solve…

13 August 2026