Choppers and concrete pours: Helicopter joins effort to deliver huge Twiggy Forrest wind farm

Published by

A helicopter has been deployed at Squadron Energy’s Uungula wind farm to start stringing the transmission lines that will connect the huge project to the grid in central western New South Wales.

Squadron said on Wednesday that a team from Leading Edge Helicopters was working closely with the project’s construction team and aviation and safety experts to attach 11km of 330 kV single circuit transmission line to 28 transmission towers over the coming months.

“This approach will support the safe, efficient and timely stringing of transmission lines at Uungula Wind Farm, which Lumea is pleased to deliver in partnership with Squadron Energy,” said Craig Stallan, executive general manager of Lumea, part of the Transgrid Group.

The 414 megawatt (MW) Uungula wind farm near Wellington in NSW will be the largest in the state, once complete – until others such as the massive, recently approved 1.45 gigawatt (GW) Yanco Delta project is built.

Squadron Energy – the renewables outfit controlled by iron ore billionaire and green energy champion Andrew Forrest – has contracted Lumea to build, operate and maintain the Uungula Wind Farm substation, switching station, and transmission lines.

Image: Squadron Energy

Squadron’s general manager of contracts and controls, Mark Hunt, says construction of the wind farm is also well underway, with concrete foundations complete for 30 of 69 turbines and turbine components, including blades, set to make the journey from the Port of Newcastle in coming months.

“I want to thank the local community, our contractors and our partners for their support to reach this stage of the project, which is creating 262 jobs and investing $41 million in the regional economy,” Hunt said on Wednesday.

“We are continuing to work hard to make sure that the project is creating a positive legacy in the region by investing in long term projects that matter to the community – including partnering with Dubbo Regional Council to deliver a new advanced wastewater treatment facility in Dubbo.”

If you would like to join more than 26,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Not a “dealbreaker:” Big Victorian wind project doesn’t need VNI West

The Macorna wind project will have a simpler ride through state planning, and insists it…

4 October 2026

Huge 195-tonne transformer arrives at big battery site after 1,300 km road trip

One of the heaviest and longest road trips ever undertaken in Australia's energy transition has…

4 October 2026

Australia is making big bets on a slow transition, but the technology S-curve tells a different story

Australia has a choice between investing in the future we can already see – or subsidising…

4 October 2026

One of Australia’s biggest wind farms forced to revisit off-take deals after lengthy construction delays and repairs

The lengthy delays at what would have been the country's biggest wind farm have forced…

3 October 2026

Still in the dark: Snowy Hydro’s awkward anniversary marked without promised review of Snowy 2 costings

The public remains largely in the dark about the full cost of the giant Snowy…

3 October 2026

Energy Insiders: Australia’s diesel dependence is not normal

Amandine Denis-Ryan from IEEFA on what can be done about Australia's unique and unhealthy dependence…

2 October 2026