Choppers and concrete pours: Helicopter joins effort to deliver huge Twiggy Forrest wind farm

Published by

A helicopter has been deployed at Squadron Energy’s Uungala wind farm to start stringing the transmission lines that will connect the huge project to the grid in central western New South Wales.

Squadron said on Wednesday that a team from Leading Edge Helicopters was working closely with the project’s construction team and aviation and safety experts to attach 11km of 330 kV single circuit transmission line to 28 transmission towers over the coming months.

“This approach will support the safe, efficient and timely stringing of transmission lines at Uungula Wind Farm, which Lumea is pleased to deliver in partnership with Squadron Energy,” said Craig Stallan, executive general manager of Lumea, part of the Transgrid Group.

The 414 megawatt (MW) Uungala wind farm near Wellington in NSW will be the largest in the state, once complete – until others such as the massive, recently approved 1.45 gigawatt (GW) Yanco Delta project is built.

Squadron Energy – the renewables outfit controlled by iron ore billionaire and green energy champion Andrew Forrest – has contracted Lumea to build, operate and maintain the Uungula Wind Farm substation, switching station, and transmission lines.

Image: Squadron Energy

Squadron’s general manager of contracts and controls, Mark Hunt, says construction of the wind farm is also well underway, with concrete foundations complete for 30 of 69 turbines and turbine components, including blades, set to make the journey from the Port of Newcastle in coming months.

“I want to thank the local community, our contractors and our partners for their support to reach this stage of the project, which is creating 262 jobs and investing $41 million in the regional economy,” Hunt said on Wednesday.

“We are continuing to work hard to make sure that the project is creating a positive legacy in the region by investing in long term projects that matter to the community – including partnering with Dubbo Regional Council to deliver a new advanced wastewater treatment facility in Dubbo.”

If you would like to join more than 26,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Solar and battery households will be biggest losers from network tariff changes, advocates say

Renewables advocacy groups join the likes of Tesla to push back against proposals to increase…

11 February 2026

Renewables auction delivers record number of solar projects, biggest onshore wind farm

The UK's latest renewable energy auction has secured a record amount of new development capacity…

11 February 2026

Canberra’s biggest battery to fund rooftop PV and storage for charities through community benefit scheme

Williamsdale battery in Canberra to fund two rooftop solar and battery storage systems for local…

11 February 2026

Another unplanned coal plant failure triggers price spike fears and supply warning

Another outage at a major coal unit triggers price spike and supply concerns, highlighting vulnerability…

11 February 2026

Energy regulator bans another company over doctored photos, false claims

Regulator bans a second company in as many weeks for allegedly using doctored photos to…

11 February 2026

Australia’s biggest coal generator learns how to make more money out of its customers and big battery fleet

AGL is making more money from customer margins and its new big batteries, but is…

11 February 2026